Decision

Lower Eype Farm, 11kV overhead line: screening decision, s37 consent, Electricity Act 1989

Screening decision to alter existing overhead line to provide necessary clearance for a new structure that is to be built.

Applies to England

Documents

Details

To replace one 12 metre pole with a new 16 metre pole on an existing 11kV overhead line to provide the clearance required for a new structure that is to be built.   Screening Decision – section 37 consent, Electricity Act 1989. 

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

17 July 2023

Section 37 consent to install or keep installed an electric line.

Published 17 July 2023