Screening decision to upgrade ~1.8km of existing 11kV overhead line to 3-phase.

Applies to England

Documents

Details

To upgrade ~1.8km of existing 11kV overhead line to 3-phase. Screening Decision – section 37 consent, Electricity Act 1989.

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

4 October 2023

Section 37 consent to install or keep installed an electric line.