Corporate report

Issued cases designated as Category B

Published 28 June 2023

Issued cases designated as Category B, having medium potential Environmental, Social and Human Rights (ESHR) impacts, where UKEF has contingent liabilities outstanding.

1. Angola

1.1 Project: The expansion and refurbishment of two substations (Gabela and Viana)

Year of issue

2018-19

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Operations

Key risks

  • Health and safety
  • Noise and air quality
  • Waste management

Monitoring summary

First operational monitoring report received; no significant E&S issues identified. UKEF agreed to waive further E&S monitoring obligations considering the small nature of E&S risks and impacts during operations and the E&S management systems in place to manage / mitigate these.

1.2 Project: Construction and equipment for 4 hospitals

Year of issue

2018-19

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Operations

Key risks

  • Health and safety
  • Labour and working conditions
  • Noise and air quality
  • Waste management

Monitoring summary

Final construction-phase report received and reviewed.

1.3 Project: Construction and operation of new livestock farms and irrigation systems

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Construction

Key risks

  • Health and safety
  • Noise and air quality
  • Biodiversity
  • Waste management
  • Animal welfare

Monitoring summary

Construction self-monitoring report received and reviewed.

1.4 Project: Construction and operation of a new substation, expansion of an existing substation, and transmission lines (Kwanza North)

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Construction

Key risks

  • Health and safety
  • Noise and air quality
  • Biodiversity
  • Waste management
  • Security

Monitoring summary

Self-monitoring report received and reviewed.

2. Bahrain

2.1 Project: Waste Water Facility Upgrade (Tubli)

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Direct Lending

Project phase

Operations

Key risks

  • Health and safety
  • Noise and air quality
  • Wastewater and waste management

Monitoring summary

First operations-phase monitoring report received and reviewed.

3. Benin

3.1 Project: Rehabilitation and upgrade of an existing road (Sogea-Satom)

Year of issue

2020-21

Applicable ESHR risk framework

OECD Common Approaches

Product

Direct Lending

Project phase

Construction

Key risks

  • Health and safety
  • Noise and air quality
  • Wastewater and waste management
  • Physical resettlement and economic displacement

Monitoring summary

Quarterly IESC monitoring reports received and reviewed.

3.2 Project: Construction and operation of a new governmental building complex

Year of issue

2022-23

Applicable ESHR risk framework

OECD Common Approaches / Equator Principles

Product

Buyer Credit Guarantee

Project phase

Construction

Key risks

  • Worker welfare and occupational health and safety;
  • Grievance mechanisms;
  • Emergency planning and response;
  • Noise, vibrations, dust and air emissions;
  • Hazardous materials, waste and drainage management;
  • Community engagement;
  • Traffic management; and
  • Land acquisition

Monitoring summary

Bi-annual monitoring report received. Some E&S issues reported, and comments made.

4. Brazil

4.1 Project: Construction of a steel plate steckel mill (Gerdau)

Year of issue

2011-12

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Operations

Key risks

  • Environmental pollution
  • Labour and working conditions
  • Health and safety
  • Waste management

Monitoring summary

No known material environmental or social issues.

5. Cameroon

5.1 Project: Rehabilitation and upgrade of an existing road and construction of ancillary infrastructures

Year of issue

2021-22

Applicable ESHR risk framework

OECD Common Approaches / Equator Principles

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Construction

Key risks

  • Health and safety
  • Labour and working conditions
  • Economic displacement
  • Noise and air quality
  • Waste management

Monitoring summary

Awaiting first self-monitoring report.

6. Côte d’Ivoire

6.1 Project: Design, construction and equipping of six regional hospitals

Year of issue

2021-22

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Construction

Key risks

  • Health and safety
  • Labour and working conditions
  • Noise and air quality
  • Waste management

Monitoring summary

Self-monitoring reports and OESMPs for some of the hospitals received. Two further OESMPs due.

6.2 Project: Rehabilitation of two existing roads and construction of four bridges

Year of issue

2021-22

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Construction

Key risks

  • Community engagement
  • Community health and safety and security
  • Land acquisition
  • Cultural heritage
  • Decommissioning and restoration

Monitoring summary

Self-monitoring report received and comments provided.

7. Finland

7.1 Project: Agricultural Facility (Rauma)

Year of issue

2017-18

Applicable ESHR risk framework

OECD Common Approaches

Product

Supplier Credit Guarantee

Project phase

Operations

Key risks

  • Fire risk
  • Health and safety
  • Waste management
  • Traffic management

Monitoring summary

UKEF to be notified in event of an incident. No incidents reported in the financial year (FY) 2022.

8. Gabon

8.1 Project: Upgrade of existing roads

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Direct Lending

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Noise and air quality
  • Economic displacement

Monitoring summary

Self-monitoring report received and reviewed. UKEF waived the requirement for further monitoring reports to be submitted, considering the low level of E&S risks and impacts in the operations phase.

9. Ghana

9.1 Project: Kumasi airport construction and upgrade, Phase II

Year of issue

2017-18

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Construction

Key risks

  • Labour and working conditions
  • Health and safety / contractor management
  • Noise and air quality

Monitoring summary

Self-monitoring report received and reviewed. Works temporarily suspended.

9.2 Project: Construction and upgrade of Kumasi market

Year of issue

2018-19

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Construction

Key risks

  • Health and safety
  • Noise and air quality
  • Wastewater and waste management
  • Physical resettlement and economic displacement

Monitoring summary

Self-monitoring reports submitted and reviewed. Works temporarily suspended from early 2023.

9.3 Project: Construction and operation of a hospital (Bekwai)

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Operations

Key risks

  • Health and safety
  • Noise and air quality
  • Wastewater and waste management

Monitoring summary

Awaiting operations phase self-monitoring report.

9.4 Project: Construction and operation of Tamale airport, Phase II

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Noise and air quality
  • Biodiversity
  • Wastewater and waste management
  • Physical resettlement and economic displacement
  • Community safety / stakeholder engagement

Monitoring summary

Awaiting operations-phase self-monitoring report.

9.5 Project: Upgrade works to Kumasi airport, Phase III

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Construction

Key risks

  • Health and safety
  • Noise and air quality
  • Wastewater and waste management

Monitoring summary

Self-monitoring report received and reviewed. Works temporarily suspended.

9.6 Project: Design, construction and equipping of a new regional teaching hospital (Kofomo Anokye)

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Direct Lending

Project phase

Construction

Key risks

  • Labour and working conditions
  • Health and safety
  • Noise and air quality

Monitoring summary

Self-monitoring report received and reviewed. Works temporarily suspended.

9.7 Project: Design, construction and equipping of a new regional teaching hospital (Koforidua)

Year of issue

2020-2021

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit / Bond Support

Project phase

Construction

Key risks

  • Labour and working conditions
  • Health and safety
  • Noise and air quality
  • Occupational health and safety;
  • Traffic management

Monitoring summary

Self-monitoring report received and reviewed. Works temporarily suspended.

9.8 Project: Redevelopment and modernization of Kumasi market, Phase II

Year of issue

2021-22

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Construction

Key risks

  • Noise, vibration and air emissions,
  • Hazardous materials, drainage, waste and wastewater management
  • Worker welfare
  • Occupational health and safety
  • Traffic management
  • Community engagement
  • Community health, safety and security
  • Economic displacement

Monitoring summary

Construction self-monitoring reports received and reviewed. Works temporarily suspended.

9.9 Project: Design and construction of a road flyover

Year of issue

2021-22

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Construction

Key risks

  • Noise, vibration and air emissions,
  • Hazardous materials, drainage, waste and wastewater management
  • Worker welfare
  • Occupational health and safety
  • Traffic management
  • Community engagement
  • Community health, safety and security
  • Livelihood restoration

Monitoring summary

Self-monitoring report received and reviewed.

10. Guyana

10.1 Project: Construction and operations of a paediatric and maternal hospital

Year of issue

2022-23

Applicable ESHR risk framework

OECD Common Approaches / Equator Principles

Product

Direct Lending

Project phase

Construction

Key risks

  • Air emissions;
  • Noise and vibrations;
  • Hazardous materials management;
  • Waste and wastewater management;
  • Water resources;
  • Emergency planning and response;
  • Worker welfare;
  • Management of third-party contractors and suppliers;
  • Occupational health and safety;
  • Traffic management;
  • Community health, safety and security

Monitoring summary

Awaiting first monitoring report.

11. Indonesia

11.1 Project: Cleaner fuel initiatives

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Construction

Key risks

  • Environmental pollution
  • Health and safety
  • Waste management

Monitoring summary

Existing operation – no monitoring requirements.

12. Iraq

12.1 Project: Construction and development of electrical substations across 15 sites (Phase I and Phase II)

Year of issue

2018-19

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Construction

Key risks

  • Labour and working conditions
  • Health and safety
  • Waste management
  • Social issues / stakeholder engagement

Monitoring summary

Self-monitoring reports received and reviewed. Construction phase nearly complete.

13. Jordan

13.1 Project: Development of an integrated garment factory

Year of issue

2022-2023

Applicable ESHR risk framework

OECD Common Approaches and Equator Principles

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Construction

Key risks

  • construction health and safety;
  • workers’ accommodation conditions;
  • worker human rights, including in the supply chain;
  • emissions to air;
  • resource efficiency and wastewater management; and
  • worker engagement and grievance mechanisms

Monitoring summary

IESC engaged. Received first monitoring report.

14. Oman

14.1 Project: Construction and operation of a new hospital (Salalah)

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Direct Lending

Project phase

Construction

Key risks

  • Labour and working conditions
  • Health and safety
  • Noise and air quality
  • Wastewater and waste management

Monitoring summary

Self-monitoring reports received and reviewed.

14.2 Project: Construction and operation of a new hospital (Khasab)

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Direct Lending

Project phase

Construction

Key risks

  • Labour and working conditions
  • Health and safety
  • Noise and air quality
  • Wastewater and waste management

Monitoring summary

Self-monitoring reports received and reviewed.

14.3 Project: Construction and operation of a new hospital (Suwaiq)

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Direct Lending

Project phase

Construction

Key risks

  • Labour and working conditions
  • Health and safety
  • Noise and air quality
  • Wastewater and waste management

Monitoring summary

Self-monitoring reports received and reviewed

15. Sri Lanka

15.1 Project: Supply and installation of single and two-lane bridges

Year of issue

2013-14

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Biodiversity
  • Waste management
  • Social issues / stakeholder engagement

Monitoring summary

UKEF to be notified in event of an incident. No incidents reported in the FY 2022.

15.2 Project: Supply and installation of single and two-lane bridges, Phase IIa and IIb

Year of issue

2014-15

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Biodiversity
  • Waste management
  • Stakeholder engagement

Monitoring summary

UKEF to be notified in event of an incident. No incidents reported in the FY2022.

15.3 Project: Supply and installation of single and two-lane bridges, Phase IIc

Year of issue

2018-19

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Biodiversity
  • Waste management
  • Stakeholder engagement

Monitoring summary

IESC report received and reviewed.

16. Togo

16.1 Project: Rehabilitation of NR14 Sokode-Tchamba-Kambole-Benin Road

Year of issue

2022-2023

Applicable ESHR risk framework

OECD Common Approaches and Equator Principles

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Construction

Key risks

  • emergency planning and response;
  • occupational health and safety;
  • management of third-party contractors and suppliers;
  • worker welfare;
  • air, noise and vibration emissions;
  • water resources;
  • waste and hazardous material management;
  • community engagement;
  • community health and safety;
  • temporary economic displacement and livelihood restoration;
  • biodiversity; and
  • cultural heritage

Monitoring summary

UKEF attended first monitoring visit along with IESC in May 2023. Some incidents reported.

17. UAE

17.1 Project: Construction and operation of the Avenue retail development, Phase II

Year of issue

2013-14

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety

Monitoring summary

Annual monitoring report received and reviewed.

17.2 Project: Construction and operation of Dubai Parks

Year of issue

2013-14

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety

Monitoring summary

No E&S incidents reported.

17.3 Project: Construction and operation of Dubai World Trade Centre, Phase I

Year of issue

2014-15

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety

Monitoring summary

Annual monitoring report received and reviewed.

17.4 Project: Construction and operation of Dubai World Trade Centre, Phase II

Year of issue

2015-16

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Contractor management
  • Waste management

Monitoring summary

Annual monitoring report received and reviewed.

17.5 Project: Construction and operation of Dubai World Trade Centre, Phase III

Year of issue

2017-18

Applicable ESHR risk framework

OECD Common Approaches and Equator Principles

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Contractor management

Monitoring summary

Annual reports received and reviewed.

17.6 Project: Construction and operation of a mixed use development on Bluewaters Island

Year of issue

2015-16

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Contractor management
  • Waste management

Monitoring summary

No E&S incidents reported. Low risk as it is operational.

17.7 Project: Construction and operation of the Al-Barsha residential blocks

Year of issue

2017-18

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Contractor management
  • Waste management

Monitoring summary

No E&S incidents reported. Low risk as the project is operational.

17.8 Project: Construction and operation of residential units (Plot 35)

Year of issue

2017-18

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Contractor management

Monitoring summary

No E&S incidents reported. Low risk as the project is operational.

17.9 Project: Construction and operation of Bee’ah head office

Year of issue

2017-18

Applicable ESHR risk framework

OECD Common Approaches

Product

Direct Lending

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Contractor management
  • Waste management

Monitoring summary

Final construction-phase self-monitoring plans received and reviewed. Operations-phase management plans finalised and accepted.

17.10 Project: Construction and operation of Dubai Arena

Year of issue

2017-18

Applicable ESHR risk framework

OECD Common Approaches and Equator Principles

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Contractor management
  • Waste management

Monitoring summary

No E&S incidents reported. Low risk as it is in operations phase.

17.11 Project: Construction and operation of Dubai World Trade Centre, Phase IV

Year of issue

2018-19

Applicable ESHR risk framework

OECD Common Approaches and Equator Principles

Product

Buyer Credit Guarantee / Direct Lending

Project phase

Operations

Key risks

  • Labour and working conditions
  • Health and safety
  • Noise and air quality
  • Waste management

Monitoring summary

Annual report received and reviewed.

17.12 Project: Construction of a new hotel in Dubai

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches and Equator Principles

Product

Buyer Credit Guarantee

Project phase

Construction

Key risks

  • Labour and working conditions
  • Health and safety
  • Biodiversity
  • Noise and air quality
  • Waste management
  • Security

Monitoring summary

Self-monitoring report received and reviewed; UKEF held a call to discuss and agree operations-phase plans as the completion is scheduled for mid-2023.

18. United Kingdom

18.1 Project: Construction and operation of a facility for the manufacturing of high voltage subsea cables for offshore wind farms

Year of issue

2022-23

Applicable ESHR risk framework

Equator Principles

Product

Export Development Guarantee

Project phase

Construction

Key risks

  • Occupational health and safety;
  • Management of third-party contractors and suppliers;
  • Noise, vibrations, dust and air emissions;
  • Hazardous materials, waste and drainage management;
  • Water and energy resources;
  • Community engagement;
  • Community health, safety and security;
  • Emergency planning and response; and
  • Biodiversity;

Monitoring summary

Awaiting first monitoring report

19. Zambia

19.1 Project: Design, construction, equipping and operation of three hospitals and 108 health centres

Year of issue

2019-20

Applicable ESHR risk framework

OECD Common Approaches

Product

Buyer Credit Guarantee

Project phase

Construction

Key risks

  • Health and safety
  • Noise quality
  • Wastewater and waste management

Monitoring summary

Monitoring reports received and reviewed. Operations-phase management plans under development.