Decision

Ducklington Farm, screening decision, s37 consent, Electricity Act 1989

Screening decision to upgrade existing 11kV overhead line from 2-phase to 3-phase and install a new H-section pole with 100kVa pole-mounted transformer.

Applies to England

Documents

Details

To upgrade ~250 metres of existing 11kV overhead line from 2-phase to 3-phase and install 1 new H-section pole with 100kVa pole-mounted transformer. Screening Decision – section 37 consent, Electricity Act 1989. 

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

11 October 2023

Section 37 consent to install or keep installed an electric line.

Published 11 October 2023