Decision

Trouble House line upgrade screening decision, S37 Consent, Electricity Act 1989

Screening decision to upgrade 3.1km of existing 11kV overhead line by replacing all poles and uprating 17 spans to 3-phase.

Applies to England

Documents

Details

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

21 November 2023

Type of project/consent requested

Section 37 consent to install or keep installed an electric line.

Published 21 November 2023