Decision

New wire and 3 phase transformer, Pick Wick Inn, St Issey: screening decision, s37 consent, Electricity Act 1989

Screening decision on installing third wire from pole number for 300m of overhead line, 3 phase transformer and lazy leg pole to support pole mounted transformer.

Applies to England

Documents

Details

To install a third wire from pole number for approximately 300m of overhead line, to install a three phase transformer and to erect a lazy leg pole to support a pole mounted transformer. Screening decision – section 37 consent, Electricity Act 1989. 

Secretary of State’s screening decisions in accordance with the Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017.

Date of decision

28 June 2023

Section 37 consent to install or keep installed an electric line.

Published 28 June 2023