UK Health Security Campus Programme: programme business case summary

Published 5 October 2026

Executive summary

The UK Health Security Campus (UKHSC) Programme will deliver world class national biosecurity infrastructure, exceptional economic value, and a resilient campus capable of protecting the country from the most dangerous infectious disease threats.

The programme comprises 2 main infrastructure construction projects:

  1. The H50 High Containment Building - the new Bioscience Facility will contain high containment laboratories for Containment Level 3 (CL3) and Containment Level 4 (CL4) (the highest biosecurity level) pathogens. The building will contain modern and enhanced facilities including suited CL4 labs. These suited facilities undertake CL4 work in air-fed suits to allow for more flexibility and a wider range of studies, compared to the traditional primary containment methods.
  2. The Main Site - including a new main building providing laboratories (CL2, CL3 SAPO 3 and CL3 SAPO 4) and office space.

As part of the Spending Review in 2025, ministers took a strategic decision to move the UK Health Security Agency (UKHSA)’s specialist scientific facilities from Porton Down, Colindale and London corporate headquarters onto one site at Harlow by 2038 and announced funding of £3.52 billion for the UKHSC Programme. This was also confirmed in UKHSA’s multi-year spending review settlement. Following the Ministerial decision, the Programme Business Case (PBC) focused on how best to deliver required services and facilities at Harlow. The PBC sought approval in principle for the full UKHSC Programme envelope (£3.52 billion) to September 2038 to begin:

  • 7 professional services procurements
  • a 2-stage Tier 1 procurement for a new main Harlow building, with demolition of the existing main building to ground level
  • reinstatement of the Pre-Construction Services Agreement with Kier for the new High Containment building (H50). If not approved, a 12 to 18-month re-procurement would be required, risking the programme’s position in the critically constrained CL4 construction supply chain, where only three UK suppliers can deliver at this scale and any disruption could significantly delay the critical path

In addition, a fundamental part of the programme is the transition of as many as possible of the approximately 2,500 roles currently working at Porton Down, Colindale and London corporate HQ into the new campus. The commitment to continue to develop a detailed workforce and people plan to support the transition of roles and colleagues, was included in the PBC.

Strategic case

Case for change

The UK needs a modern and resilient health security campus to detect, assess and respond to the most serious threats to the nation’s public health and protect the country from the most dangerous infectious disease threats. The top national security risks in the National Risk Register (2025) are a future pandemic or malicious biological attack. Both have potentially devastating impacts for public health and the economy.

UKHSA’s current scientific and high containment laboratory infrastructure is located primarily at Porton Down (Wiltshire) and Colindale (North London). These facilities are essential for characterising dangerous and unknown pathogens, disease surveillance, managing and responding to outbreaks, and conducting the necessary research to develop and validate new vaccines, diagnostics and therapeutics. UKHSA’s high containment laboratories are essential for protecting public health and saving lives. The current high containment facilities need to be modernised and upgraded to ensure UKHSA can continue to detect and investigate high consequence pathogens in the long term. Investing now will drive efficiencies, reduce maintenance costs, minimise business disruption and continue essential health protection functions that enable scientific innovation. Further to this, the UKHSC will add substantial social value to Harlow through the creation of local jobs, supporting an area that is set to undergo large-scale regeneration, including the build of a new hospital and new homes.

Located within the London to Cambridge Innovation Corridor, the UKHSC will deliver transformational change, consolidating existing fragmented sites onto one campus for as many as possible of the approximately 2,500 UKHSA staff, driving productivity, faster science, and operational resilience. The Innovation Corridor is the UK’s strongest life sciences labour market, enabling recruitment and retention of specialist scientists – ensuring that the UK remains a global leader in biosecurity and enabling improved research and development and innovation through co-location and collaboration. This is in line with similar global programmes that have co-located sites in urban innovation hubs to drive valuable public-private partnerships.

The UKHSC will be one of the leading National Biosecurity Centres (NBCs) in Europe and will be part of the Government’s National Biosecurity Centre Network alongside NBC Weybridge (Animal and Plant Health Agency (APHA)) and NBC Porton Down at Defence Science and Technology Laboratory (Dstl) to enhance the UK’s resilience against biological threats. This delivers the vision of the UK Government’s Biological Security Strategy (2023), taking a ‘One Health’ approach to biosecurity, integrating expertise across human, animal, and environmental health.

Beyond this, the UKHSC supports the delivery of a range of key government priorities and initiatives across the health family and government:

An NHS fit for the future: ‘from sickness to prevention’: the programme will support a shift from treatment to prevention in line with the NHS 10 Year Plan through faster vaccine, diagnostic and therapeutic development, and improved early detection of disease threats.

Economic growth through innovation: bringing the UK in line with global innovation hubs, the UKHSC will attract top talent, strengthen public-private partnerships in the London to Cambridge Innovation Corridor and drive economic growth through employment opportunities and innovation within the life sciences sector, as set out in the Cross-Government Life Sciences Sector Plan (2025).

Ensuring every region reaches its potential: UKHSA’s relocation will deliver increased skilled employment opportunities in Harlow for an area currently characterised by below average employment levels and household income and is aligned with the wider Harlow Town Regeneration Programme.

Delivery of Net Zero by 2050: as a transformational estates project, the UKHSC will contribute to the UK’s 2050 net zero target through energy efficiency and consolidated estate.

Strategic objectives

The programme has 5 broad strategic objectives which reflect the broader transformation mission for UKHSA and are weighted for their importance.

  1. Ensure business continuity of UKHSA’s critical scientific and health security services through the replacement of ageing infrastructure.
  2. Strengthen emergency preparedness and national resilience.
  3. Improved collaboration and productivity.
  4. Ensure UKHSA’s ability to continue to retain and attract top scientific and expert talent.
  5. Deliver sustainable facilities that, where possible, meet UK environmental targets.

Economic case

Shortlisted options

The Business Case considered a range of options for delivery of the UK Health Security Campus:

Business As Usual (BAU): maintaining current facilities at Porton Down and Colindale, with Corporate HQ remaining in London. This option retains current CL2, CL3 and CL4 laboratory capabilities and relies on ongoing maintenance and repair of ageing facilities, with no significant enhancements to capability, capacity or operational flexibility.

Harlow Do Minimum: co-location of facilities in Harlow, but with Corporate HQ remaining in London. This option provides modern, flexible CL2, CL3 and CL4 laboratories, increased CL3 and CL4 capacity to meet future demand, and an education centre for training and outreach, but does not enhance CL4 capability beyond current operational requirements.

Harlow Central (preferred): co-location of all scientific facilities in Harlow including Corporate HQ and improved CL4 capability. This option provides modern and flexible CL2, CL3 and CL4 laboratories, increased capacity, enhanced CL4 capability through the inclusion of suited facilities, standardised laboratory equipment and an education centre for training and outreach.

Harlow Advanced: co-location of all scientific facilities in Harlow including Corporate HQ and improved CL4 capability. This option provides modern and flexible CL2, CL3 and CL4 laboratories, increased capacity, enhanced CL4 capability through the inclusion of suited facilities, standardised laboratory equipment and an education centre for training and outreach. This option also has an additional building that will function as a partner collaboration space.

Costs, benefits and risks of shortlisted options

The programme applied social cost-benefit analysis in line with HMT Green Book Guidance. The preferred option (Harlow Central) delivers the strongest economic performance of the shortlisted options. It has a Net Present Social Value (NPSV) of £6.70 billion, representing the total value of benefits to society after programme costs have been deducted, and a BCR of 4.77. By comparison, Harlow Do Minimum has an NPSV of £0.44 billion (BCR 1.30), and Harlow Advanced has an NPSV of £6.43 billion (BCR 4.09). Even under conservative sensitivity tests (halved vaccine acceleration, reduced productivity uplift), the BCR remains above 2.7.

Results from the value-for-money assessment are summarised below:

Present value in Harlow Central option
Incremental monetisable benefits versus BAU  
Total incremental benefits £8.48 billion
Incremental costs versus BAU  
Total incremental costs £1.78 billion
Value for money  
Net present social value £6.70 billion
Benefit cost ratio 4.77

In the Harlow Central option, mitigated optimism bias adjustment of 15% was applied to capital costs. Adjustments to benefits to account for optimism were made according to the benefit. This application of Optimism Bias is in line with Green Book guidance.

Harlow Central generates £8.48 billion in monetisable benefits. The monetisable benefits of the preferred option include:

  • avoided health and economic costs of disease outbreaks - from faster vaccine rollout, co-location productivity uplift, reduced risk of outages
  • cost savings from rationalisation of estate and economies of scale - the programme will enable the consolidation and de-duplication of roles, contracts and facilities across UKHSA’s existing sites
  • internal productivity uplift from co-location - this will support increased collaboration between teams, leading to a boost in productivity across several service domains

Beyond monetisable benefits, the preferred option allows delivery of strategically critical, non-monetised advantages, including:

  • reduced likelihood of outbreaks establishing in the UK through strengthened high containment capability, diagnostics and international engagement
  • workforce resilience and talent attraction/retention due to a new location in the London-Cambridge Innovation Corridor, the UK’s strongest life sciences labour market, providing greater access to the leading scientific talent of the future
  • knowledge spillovers and collaboration-led innovation across the life sciences ecosystem

These benefits, as well as others, were developed and validated through structured workshops, subject matter expert (SME) advisory sessions and economist engagement – ensuring that all assumptions are evidence based. Workshops were also undertaken to carry out a risk assessment across the shortlisted options. The impact and likelihood of each risk was assessed on a 5-point scale: from low (1) to high (5), with weightings assigned to the risks to assess the relative importance of each.

The highest weighted risks included:

  • programme may fail to meet regulatory, Health & Safety, biosecurity and policy requirements
  • programme may face reduced funding
  • UKHSA may face challenges to retain its existing workforce as a consequence of the programme
  • programme may face material cost pressures

Based on the top-level risks considered in the full appraisal, Harlow Central was identified as the lowest risk option and performed the best in relation to the strategic, financial, design and legal/compliance risks of the programme.

The shortlisted options were also assessed against Strategic Objectives and Critical Success Factors (CSF) through workshops with key stakeholders. Harlow Central scored consistently highest (or jointly highest) across these assessments.

Preferred option and rationale

The programme’s appraisal of credible options concluded that Harlow Central provides the strongest overall value and meets UKHSA’s core scientific, operational and organisational needs within the approved £3.52 billion funding envelope.

The preferred option is expected to deliver a benefit-cost ratio (BCR) of 4.77, meaning that every £1 invested is expected to generate approximately £4.77 of benefits for society. Harlow Central also scored highly on the assessment of non-monetisable benefits, remains within the overall programme budget (£3.52 billion), and demonstrates the lowest weighted risk score among viable options, making it the most balanced and value-optimising option.

Commercial case

The proposed commercial and procurement strategy for the different capabilities required for delivery of the programme is detailed in the Commercial Case.

The programme’s history of pause and re-commencement has resulted in a fragmented commercial contractual landscape, with all previous contracts terminated, expired or placed into suspension. The Commercial Case therefore addresses the appropriate treatment of existing contractual arrangements considering the programme’s updated requirements.

The procurement strategy and plans for delivery

The commercial strategy for delivering the preferred option for the UK Health Security Campus is structured around 3 delivery pillars. Detailed market analysis and engagement was undertaken to assess capacity, capability and appetite across professional services delivery partners (Pillar 2) and Tier 1 Construction Contractor (Pillar 3) markets. This informed the proposed procurement approach including delivery model, packaging and contracting strategy.

Pillar 1

Pillar 1 relates to all the short-term contracts (between June 2025 and March 2027) required to mobilise the programme at pace. This is out of scope of the PBC.

Pillar 2

Pillar 2 relates to the Long-Term Programme Delivery Partner requirements, covering specialist professional services capabilities required to deliver the programme from financial year (FY) 2027 to 2028.

Several options were considered as part of the delivery of requirements for Pillar 2, which all relate to Construction Professional Services Capabilities. A detailed Delivery Model Assessment (DMA) was undertaken across 4 delivery models.

The recommended approach for Pillar 2 is to structure the required capabilities into 7 distinct work packages by different capabilities.

Pillar 3

Pillar 3 relates to the Tier 1 Construction Delivery Partners, covering the design, build, commissioning and validation of the Harlow site.

The recommended approach keeps the high containment building as a standalone contract – separate to the remainder of the Harlow site. The high containment building is the most complex facility on site with it being the only facility that will have Containment Level 4 (the highest level of containment) laboratories – and the first in the UK with suited capability for public health.

The DMA analysed the different packaging options and demonstrated that two work packages for the high containment building and Main Site, with some optionality for how demolition of the current main building is delivered (subject to further analysis), is the optimum way to deliver the construction requirements of the programme. This approach balances the need for reducing contractual interfaces for the whole site with appropriate mitigation of a single point of failure risk.

Finance case

The finance case outlines the affordability and funding requirements for the preferred option.

It shows that the programme is affordable within the £3.52 billion envelope and delivers on time (by September 2038). As design and delivery plans are further developed to a detailed level, a final profile of spend by year will be confirmed in the PBC addendum to be completed in 2027.

The total expected costs of the preferred option include:

  • £3,022 million (86%) capital costs
  • £503 million (14%) revenue costs

Combined capital and revenue risk allowance is £516 million net, or £665 million gross, split across costed risk (£279 million) and programme risk (£386 million).

The largest cost pressures arise from the specialist construction of H50 and the Main Science Building, together with substantial allowances for risk, inflation and VAT. These are then supplemented by transition-related costs, particularly workforce transition, dual running and programme management. Much of the cost is driven by the highly specialised nature of the H50 CL4 facility, which requires specialist design, construction and validation capabilities. Cost pressures are mitigated by maintaining the current critical path, which protects access to a highly constrained CL4 supply chain and avoids a 2-year programme delay.

Construction costs

UKHSA engaged independent cost assurers to produce updated construction cost assessments for the preferred option. These costs were refined through various adjustments including additional fees and top-down benchmarking. In addition to the build costs, capital costs include £130 million for non-construction costs such as capitalisable internal staff, purchase of equipment and Harlow site running costs.

Together with construction inflation and risk allowances discussed elsewhere, these costs contribute to the total capital cost estimate of £3,022 million.

Transition costs

Transition costs represent the revenue investment required to move scientific and other operations from Porton, Colindale and 10SC to the new Harlow site, covering staff capacity building, people transition, dual running of old and new facilities during validation, the physical move of equipment, demolition and preparation of legacy sites, and programme wide management costs. These costs totalled £503 million (RDEL).

Whole life costs (post investment)

As well as the investment analysis over 13 years, whole life costs were projected for each option for a period of 60 years post investment, totalling a 73-year period. This shows that the preferred option delivers clear financial advantages over realistic time horizons. For the preferred option, capital life-cycle costs are projected at £14.1 billion over the full 60-year post-implementation period – this will be funded from BAU expenditure after the completion of the programme.

60-year post investment whole-life cost modelling shows that the preferred option provides long-term revenue financial sustainability, with reduced duplication, estate consolidation and lower revenue running costs compared to BAU. Over 10- and 25-year horizons, the preferred option is demonstrated to be cheaper than BAU in CDEL terms; over 60 years it becomes cheaper still if BAU capital maintenance rises to levels considered likely for an ageing estate.

Summary of key assumptions

The finance case has been developed on a prudent basis, deliberately avoiding optimistic assumptions about income generation or cost savings. The approach taken provides sufficient allowance for uncertainty, whilst avoiding unnecessary inflation of totals.

Inflation has been applied to all future costs, and given the length of the programme, it represents a significant component of overall financial profile.

Value added tax (VAT) is included in financial modelling at 20% on applicable costs. All VAT expended on the programme investment is currently assumed to be non-recoverable.

Summary of key financial risks

Key financial risks include:

  • availability of funding, approvals and macro climate
  • construction delay (for instance from delays in lead times, weather and unknowns)
  • programme subject to further significant design changes and / or experiences ‘scope creep’
  • supplier availability and behaviours
  • transition risk and operational readiness for the move
  • cost escalation and inflation

Robust governance, risk management, and financial control arrangements are in place to monitor these risks, track mitigations and ensure timely escalation where necessary.

Management case

The UK Health Security Campus Programme is part of the UK government’s Major Projects Portfolio. We continue to work closely with the National Infrastructure and Service Transformation Authority to ensure successful delivery of the programme.

A delivery plan is in place covering key activities and milestones which are tracked and managed through the established governance structure.

Governance arrangements

Programme governance is multi-layered, ensuring clear lines of responsibility, accountability, decision-making and alignment with financial delegations. Governance arrangements provide clear decision making, escalation routes, representation of key stakeholders, and compliance with departmental delegated authority thresholds. The programme uses the 3 lines of defence model to ensure assurance and oversight throughout the organisation and with cross-government scrutiny and support.

The UKHSC Programme governance model includes the core programme management meetings and governance forums, and is supported by a host of senior executives and user groups, including a dedicated SRO, Programme Director, and a skilled Programme Board. These will support successful delivery of the programme and ensure fair and robust representation of the key internal and external stakeholders.

Key programme milestones

The programme has an integrated master schedule, developed with suppliers and subject matter experts, ensuring consistency across delivery teams and project functions, alignment of stakeholders, and provides a single central source of information for monitoring and controlling project execution against set baselines and objectives. The master schedule is supported by a full Integrated Assurance and Approvals plan, covering investment decisions, assurance reviews and the design assurance process.

The programme’s high-level milestones are detailed below:

Milestone Date
PBC approval July 2026
Start of main construction works (with early works from 2028) Quarter 4 2029
Start of validation and dual running Quarter 1 2034
Start of personnel deployment Mid-2030s onwards
Health Security Campus complete and in service September 2038

Dependencies

The programme’s success depends on several factors. These include:

HM Government’s continued commitment to the programme to ensure future programme funding is prioritised, and the full required SR envelopes are agreed.

Sufficient organisational capacity to ensure subject matter experts have capacity to input throughout the design and development process. Public health emergencies requiring the focus of BAU teams could impact on organisational capacity to support the programme.

Maintaining the existing position in the market and availability of specialist suppliers for specialist laboratory construction, given specific methodology and experience required for high containment buildings. Small supply chains and multiple programmes mean the UKHSC is dependent on suppliers having sufficient capacity.

Building a specialist workforce to include local talent in Harlow. This will include recruitment for dual running as the Harlow site starts to come online and for whole life support across the site.

Local authorities remaining engaged to support planning permission applications and ensure construction progresses smoothly.

Approach to risk management summary

A comprehensive Risk Management Strategy applies to all projects within the wider programme and to all staff involved in delivering the Programme’s objectives. Risk, Assumption, Issue and Dependency (RAID) Management is integrated, pragmatic and proactive – promoting a culture of ownership and of continuous improvement. Risk management principles are aligned to the international risk management standard, ISO 31000.

All risks are quantified (either qualitatively or quantitatively), and impacts measured in cost, time and deliverables, as well as Health and Safety, operations, reputation and legal.

The programme prioritises timely delivery of facilities, strict compliance, safety, and security, while maintaining cautious approaches to cost, environmental impact, and stakeholder satisfaction. The risk management process is supported by a governance structure that defines the roles and responsibilities at each stage of the Programme.

Evaluation plan summary

The post implementation evaluation will comprise a detailed examination of the extent to which the project has succeeded in fulfilling its original objectives and will draw on the monitoring information. The Evaluation will include a full process and impact evaluation with a value for money assessment and will be integrated with the Programme Benefits Realisation Plan to form one product that will provide the controls for the collection of evidence and the management of benefits.

As part of infrastructure and construction project evaluation, following handover and operation, there will be regular formal Post Occupancy Evaluation Assessments to measure and monitor the benefits realisation, and as part of continuous improvement.

Corporate transition

Corporate transition is a fundamental part of the programme which encompasses the transition of both people and core UKHSA services to the UKHSC in Harlow. This transition will see as many as possible of the approximately 2,500 roles currently working out of Porton Down, Colindale and London corporate HQ move into the new campus. The corporate transition costs form part of the £503 million revenue transition costs (RDEL) outlined in the finance case.

People transition costs are currently estimated at £95 million. This figure reflects the projected costs of a host of people-related initiatives and arrangements that will be required to support staff throughout the transition to the UKHSC. These arrangements will be developed over time as the Programme progresses and we form a robust people plan, which will be underpinned by continuous workforce planning.

Capacity building costs are currently estimated at £45 million – this is the pre-emptive building of staff capability and capacity ahead of the move from existing scientific sites at Porton and Colindale to Harlow. Requirements for capacity building will be developed and detailed within our workforce planning.

Dual running is a key part of the overall transition, and the net present cost of dual running has currently been estimated at £79 million. During this period, staff will be required to work at both old and new sites. The need for staff, consumables, service and space will be duplicated to an extent; detailed plans of dual running will mature in the coming years as the programme progresses.

Our overall focus during this transition is to provide the right support for our people through this significant change through effective change management. There will be a focus on engagement and wellbeing, to fully understand and seek to address the impact of this transition on our colleagues. Support will be provided across the organisation to ensure that the right capabilities are at the UKHSC when functional activity commences. This will aim to reduce any disruption to the business and mitigate against any risks to business continuity as a result of transition.