All data is correct as of 1 August 2026 and provided by the Building Safety Regulator (BSR).
Introduction
This is an updated and expanded dataset for our July data publication.
As in previous months, this BSR dataset includes information relating to gateway 2 performance, with the London area performance separate.
We also include data on our internal and external resource usage, as well as early data on gateway 3 performance.
New information this month includes:
| Status |
New higher-risk buildings (HRBs) and conversions |
External remediation |
| Cases in progress |
131 |
330 |
| Invalid or withdrawn |
15 |
19 |
| Decisions made |
45 |
110 |
| New in |
53 |
103 |
| Approval rate |
91% |
85% |
| Median approval time |
22 weeks |
34 weeks |
| Units approved |
7,587 |
7,433 |
- August 2026 marks 12 months since the Innovation Unit was set up to deal exclusively with new build HRB applications.
- At that point, median approval time for new builds was at 43 weeks with an approval rate of 39%.
- Now, median approval time is 22 weeks with an approval rate of 91%.
- Over the same period, performance of external remediation applications also improved significantly. Approval times fell from 43 weeks to 34 weeks, and approval rates increased from 47% to 85%.
Gateway 2: headline numbers for May to July 2026 – internal works and NHS
| Status |
Internal works |
NHS applications |
| Cases in progress |
981 |
36 |
| Invalid or withdrawn |
257 |
9 |
| Decisions made |
166 |
19 |
| New in |
448 |
29 |
| Approval rate |
77% |
84% |
| Median approval time |
32 weeks |
24 weeks |
- We’re reporting NHS applications as a separate category for the first time. Previously, they’ve been reported on within the HRB internal works dataset.
- These can include a range of building work in hospitals, from maintenance to new hospital facilities.
- We have been working closely with the NHS to facilitate the specialist nature of their applications.
- This has started to show positive results, with some recent approvals coming in at the statutory 8-week timescale.
- The median approval time for NHS applications submitted in 2026 has reduced to 13 weeks.
- Showing a similar pattern, the median approval time for HRB internal works applications submitted in 2026 has reduced to 16 weeks.
- Overall median approval times are higher as we continue to close applications from 2025.
All application categories
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 11 May |
72 |
122 |
1,521 |
| 18 May |
57 |
88 |
1,490 |
| 25 May |
42 |
53 |
1,479 |
| 1 June |
81 |
58 |
1,502 |
| 8 June |
55 |
49 |
1,508 |
| 15 June |
55 |
49 |
1,514 |
| 22 June |
53 |
48 |
1,519 |
| 29 June |
55 |
37 |
1,537 |
| 6 July |
51 |
39 |
1,549 |
| 13 July |
46 |
56 |
1,539 |
| 20 July |
45 |
38 |
1,546 |
| 27 July |
46 |
45 |
1,547 |
- There are currently 1,547 gateway 2 applications in progress, a slight drop over the past 12 weeks.
- These include the new build, external remediation, internal refurbishment and NHS applications.
- This data also includes transitional cases. These are projects that revert to BSR when the building control body that was originally overseeing the project stops trading.
- Commenced under the previous building control regime, they are generally more complicated to progress. This is because much of the evidence that we now expect at gateway 2 is not available.
- There are currently 69 transitional cases in progress at gateway 2.
New HRBs and conversions (national)
New HRBs and conversions: new in versus closed decisions (national)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 11 May |
5 |
5 |
138 |
| 18 May |
9 |
5 |
142 |
| 25 May |
3 |
10 |
135 |
| 1 June |
7 |
3 |
139 |
| 8 June |
2 |
3 |
138 |
| 15 June |
4 |
5 |
137 |
| 22 June |
4 |
4 |
137 |
| 29 June |
2 |
5 |
134 |
| 6 July |
2 |
2 |
134 |
| 13 July |
7 |
9 |
132 |
| 20 July |
4 |
4 |
132 |
| 27 July |
4 |
5 |
131 |
| Description |
Total |
| New in |
53 |
| In progress |
131 |
| Units approved |
7,587 |
| Units in progress |
30,421 |
New HRBs and conversions percentages and weeks taken (national)
In the period, there were:
- 45 decisions made
- 15 invalid or withdrawn applications
- 29 complex cases in progress with a median approval time of 32 weeks
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
9% |
6 |
| Approval rate |
91% |
22 |
- Out of 53 applications received over the past 12 weeks, 9 applications were invalidated and 6 withdrawn. Of the 45 decisions made, 41 were approvals and 4 were rejections.
- This means that the 12-week rolling approval rate (not including invalidations and withdrawals) has risen to 91%, with the median approval time steady at 22 weeks.
- For comparison, in the 12 weeks to August 2025, median approval time was at 43 weeks with an approval rate of 39%.
- Complex cases are tracked separately and, whilst the final decision is included in the rejection or approval totals, their median approval time is now at 32 weeks.
- We continue to work closely with industry on a shared understanding of compliance as we try to reduce the number of complex cases in the system.
- The overall combined total is sitting at 131 and has declined slightly over the past month.
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 11 May |
7 |
4 |
359 |
| 18 May |
9 |
7 |
361 |
| 25 May |
9 |
7 |
363 |
| 1 June |
10 |
16 |
357 |
| 8 June |
9 |
12 |
354 |
| 15 June |
7 |
15 |
346 |
| 22 June |
11 |
9 |
348 |
| 29 June |
16 |
12 |
352 |
| 6 July |
8 |
13 |
347 |
| 13 July |
5 |
16 |
336 |
| 20 July |
9 |
7 |
338 |
| 27 July |
3 |
11 |
330 |
| Description |
Total |
| New in |
103 |
| In progress |
330 |
| Units approved |
7,433 |
| Units in progress |
28,778 |
In the period, there were:
- 110 decisions made
- 19 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
15% |
34 |
| Approval rate |
85% |
34 |
- The rolling 12-week approval rate has stayed at 85%, with the median approval time dropping from 35 to 34 weeks. This remains above target due to the inclusion of decisions on older cases, which have been in the system for some time.
- 13 legacy applications made in 2024 now remain, down from 42 at the start of 2026.
- We also continue to work closely with the sector to help applicants improve the quality of applications.
- This, along with increased resources and more efficient processes, is showing positive results. The median approval time for external remediation applications submitted in 2026 is now at 21 weeks.
- New guidance setting out what level of detail is expected in applications and common shortfalls was published on 22 June 2026.
HRB internal works (national)
HRB internal works: new in versus closed decisions (national)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 11 May |
53 |
103 |
906 |
| 18 May |
35 |
66 |
875 |
| 25 May |
28 |
32 |
871 |
| 1 June |
61 |
31 |
901 |
| 8 June |
37 |
27 |
911 |
| 15 June |
38 |
24 |
925 |
| 22 June |
34 |
34 |
925 |
| 29 June |
33 |
18 |
940 |
| 6 July |
36 |
21 |
955 |
| 13 July |
28 |
22 |
961 |
| 20 July |
28 |
20 |
969 |
| 27 July |
37 |
25 |
981 |
| Description |
Total |
| New in |
448 |
| In progress |
981 |
HRB internal works: percentages and weeks taken (national)
In the period, there were:
- 166 decisions made
- 257 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
23% |
33 |
| Approval rate |
77% |
32 |
- The approval rate for internal refurbishment works in category A and B is currently 77%, with a median determination time for approvals of 32 weeks.
- Determination times have risen since the last publication as we have closed a significant number of older applications in recent months.
- This masks the fact that more recent applications are moving through the system more rapidly. The median determination time for internal works applications submitted in 2026 is currently 16 weeks.
-
HRB internal work determinations over the past 12 weeks account for around 49% of all gateway 2 decisions. These applications include all internal refurbishment works except NHS.
NHS applications (national)
NHS applications: new in versus closed decisions (national)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 11 May |
5 |
2 |
38 |
| 18 May |
1 |
4 |
35 |
| 25 May |
0 |
1 |
34 |
| 1 June |
1 |
3 |
32 |
| 8 June |
1 |
3 |
30 |
| 15 June |
5 |
2 |
33 |
| 22 June |
3 |
1 |
35 |
| 29 June |
2 |
0 |
37 |
| 6 July |
2 |
2 |
37 |
| 13 July |
5 |
4 |
38 |
| 20 July |
2 |
5 |
35 |
| 27 July |
2 |
1 |
36 |
| Description |
Total |
| New in |
29 |
| In progress |
36 |
NHS applications: percentages and weeks taken (national)
In the period, there were:
- 19 decisions made
- 9 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
16% |
11 |
| Approval rate |
84% |
24 |
-
NHS applications are now shown separately from HRB internal works.
- The approval rate for NHS internal refurbishment is currently 84%.
- Some more recent applications have been determined at, or close to, the statutory 8-week target.
- The median approval time for NHS applications submitted in 2026 has reduced to 13 weeks.
- However, the overall median determination time for approvals is at 24 weeks as we close older applications.
Gateway 2: regional distribution
Data as of 1 August 2026.
Regional gateway 2 applications (London)
| Region |
New HRBs and conversions |
remediation |
HRB internal works |
NHS |
Transitional |
| London |
85 |
187 |
653 |
15 |
32 |
| Rest of England |
37 |
142 |
311 |
20 |
33 |
Regional gateway 2 applications (rest of England)
| Region |
New HRBs and conversions |
remediation |
HRB internal works |
NHS |
Transitional |
| East |
0 |
17 |
40 |
2 |
1 |
| East Midlands |
0 |
12 |
25 |
1 |
1 |
| North East |
0 |
8 |
32 |
5 |
2 |
| North West |
18 |
42 |
34 |
1 |
15 |
| South East |
6 |
30 |
32 |
3 |
4 |
| South West |
3 |
20 |
70 |
3 |
5 |
| West Midlands |
4 |
2 |
30 |
1 |
1 |
| Yorkshire and The Humber |
5 |
11 |
38 |
4 |
4 |
New HRBs and conversions (London)
New HRBs and conversions: new in versus closed decisions (London)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 11 May |
5 |
3 |
88 |
| 18 May |
7 |
4 |
91 |
| 25 May |
3 |
4 |
90 |
| 1 June |
4 |
2 |
92 |
| 8 June |
1 |
2 |
91 |
| 15 June |
1 |
4 |
88 |
| 22 June |
3 |
2 |
89 |
| 29 June |
2 |
3 |
88 |
| 6 July |
0 |
2 |
86 |
| 13 July |
3 |
3 |
86 |
| 20 July |
2 |
3 |
85 |
| 27 July |
2 |
2 |
85 |
| Description |
Total |
| New in |
33 |
| In progress |
85 |
| Units approved |
3,841 |
| Units in progress |
17,552 |
New HRBs and conversions: percentages and weeks taken (London)
In the period, there were:
- 27 decisions made
- 7 invalid or withdrawn applications
- 21 complex cases in progress with a median approval time of 31 weeks
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
7% |
6 |
| Approval rate |
93% |
23 |
- Around 65% of in-progress new build applications are in London.
- This also represents around 58% of the overall new build residential units handled by BSR.
- 25 of the 45 new build decisions made in the last 12 weeks are in London.
- London approval rates are 93%. This figure reflects the significant effort that has gone in to resolve outstanding complex cases.
- Approval time for non-complex cases is 23 weeks, slightly above the national average.
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 11 May |
4 |
1 |
198 |
| 18 May |
7 |
3 |
202 |
| 25 May |
6 |
3 |
205 |
| 1 June |
6 |
10 |
201 |
| 8 June |
4 |
4 |
201 |
| 15 June |
4 |
9 |
196 |
| 22 June |
7 |
5 |
198 |
| 29 June |
4 |
3 |
199 |
| 6 July |
3 |
6 |
196 |
| 13 July |
4 |
7 |
193 |
| 20 July |
4 |
6 |
191 |
| 27 July |
2 |
6 |
187 |
| Description |
Total |
| New in |
55 |
| In progress |
187 |
| Units approved |
3,422 |
| Units in progress |
15,814 |
In the period, there were:
- 52 decisions made
- 11 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
8% |
27 |
| Approval rate |
92% |
31 |
- Open remediation cases in London have dropped over the period from 195 to 187.
- We announced the BSR remediation improvement plan in April 2026.
- We have already made progress with 13 legacy 2024 applications now remaining, down from 42 at the start of 2026.
- The median approval time in weeks based on the rolling total shows our effort on closing older 2024 to 2025 applications. This is affecting the overall median approval times.
- Applications submitted in 2026 are being determined much more quickly.
- 2026 approval rates already exceed the greater than 65% target for 2026 at 85%.
- London approval rates of 95% are slightly higher than they are nationally.
HRB internal works (London)
HRB internal works: new in versus closed decisions (London)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 11 May |
22 |
72 |
580 |
| 18 May |
23 |
38 |
565 |
| 25 May |
23 |
20 |
568 |
| 1 June |
37 |
23 |
582 |
| 8 June |
27 |
14 |
595 |
| 15 June |
32 |
18 |
609 |
| 22 June |
22 |
21 |
610 |
| 29 June |
22 |
9 |
623 |
| 6 July |
25 |
11 |
637 |
| 13 July |
18 |
16 |
639 |
| 20 July |
20 |
13 |
646 |
| 27 July |
27 |
20 |
653 |
| Description |
Total |
| New in |
298 |
| In progress |
653 |
HRB internal works: percentages and weeks taken (London)
- 108 decisions made
- 167 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
24% |
37 |
| Approval rate |
76% |
30 |
- The approval rate for internal refurbishment works in categories A and B is currently
76%, with a median determination time of 27 weeks for approvals. This is very similar
to the national average.
- The overall combined total is less than would be expected in steady state, currently
sitting at 653, having increased slightly over the past 12 weeks.
-
HRB internal work determinations over the past 12 weeks account for around 66% of
gateway 2 decisions in London. These applications include all internal refurbishment works except NHS applications.
NHS applications (London)
NHS applications: new in versus closed decisions (London)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 11 May |
2 |
0 |
15 |
| 18 May |
0 |
1 |
15 |
| 25 May |
0 |
1 |
14 |
| 1 June |
0 |
1 |
13 |
| 8 June |
0 |
1 |
12 |
| 15 June |
3 |
0 |
14 |
| 22 June |
0 |
0 |
14 |
| 29 June |
2 |
0 |
16 |
| 6 July |
2 |
0 |
18 |
| 13 July |
1 |
2 |
17 |
| 20 July |
0 |
2 |
15 |
| 27 July |
0 |
0 |
15 |
| Description |
Total |
| New in |
10 |
| In progress |
15 |
| Units approved |
6 |
| Units in progress |
15 |
NHS applications: percentages and weeks taken (London)
In the period, there were:
- 7 decisions made
- 1 invalid or withdrawn application
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
14% |
10 |
| Approval rate |
86% |
27 |
-
NHS applications have now been split from HRB internal works.
- The approval rate for NHS internal refurbishment works is currently 86%, with a median determination time for approvals of 27 weeks. This is slightly higher than the national average.
Building control resources: people working on building control applications
| Week commencing |
Internal resources |
External resources |
Total resources |
| 11 May |
96 |
247 |
343 |
| 18 May |
102 |
256 |
358 |
| 25 May |
91 |
235 |
326 |
| 1 Jun |
103 |
277 |
380 |
| 8 Jun |
110 |
281 |
391 |
| 15 Jun |
115 |
262 |
377 |
| 22 Jun |
122 |
256 |
378 |
| 29 Jun |
134 |
252 |
386 |
| 6 Jul |
142 |
254 |
396 |
| 13 Jul |
149 |
261 |
410 |
| 20 Jul |
144 |
255 |
399 |
| 27 Jul |
137 |
206 |
343 |
| Description |
Total |
| Internal resources |
137 |
| External resources |
206 |
| Integrated resources |
65 |
Building control resources: resource breakdown
Internal resources
| Description |
Total |
| Regulatory leads |
100 |
| Principal regulatory leads |
15 |
| Case officers |
56 |
| Case officer managers |
5 |
External resources
| Description |
Total |
| Registered building inspectors |
221 |
| Fire service professionals |
111 |
| Structural engineers |
135 |
| Specialists |
39 |
Integrated resources
| Description |
Total |
| Registered building inspectors |
36 |
| Fire service professionals |
7 |
| Structural engineers |
22 |
- Sufficient internal, external and integrated resources are essential for BSR to meet demand. We have grown our internal regulatory team by 25 over the past 3 months, and we are continuing to actively recruit over the next 6 to 12 months. We are also growing our integrated resource teams to meet demand, see the ‘Building control integrated resources’ section.
- 176 internal staff members have been involved in building control applications, including 100 regulatory leads, 15 principal regulatory leads, 56 case officers, 5 case officer managers.
- 506 people from external organisations have been involved in building control applications, including 221 registered building inspectors, 111 fire service professionals, 135 structural engineers, 39 specialists.
- Of the 506 people sourced or seconded from external organisations, 65 are integrated into BSR’s Innovation Unit or external remediation teams. This includes 36 RBIs, 7 fire service professionals and 22 structural engineers.
Building control integrated resources
BSR has several specialist resources working as part of an integrated workforce within the new build and external remediation teams. We are growing this capacity to meet demand and reduce processing times.
Note that full-time equivalent (FTE) is an aggregated total of staff availability, as some people are available fewer than 5 days per week.
| Resource |
FTE as of 31 July |
Headcount as of 31 July |
August forecast (FTE) |
September forecast (FTE) |
October forecast (FTE) |
| Registered building inspectors |
23.3 |
36 |
25.3 |
29.3 |
34.3 |
| Structural engineers |
20 |
22 |
20 |
21 |
25 |
| Fire service professionals and engineers |
6.6 |
7 |
6.6 |
6.6 |
11.6 |
| Total |
49.9 |
65 |
51.9 |
56.9 |
70.9 |
In build: major changes from May to July 2026
Data as of 1 August 2026.
In build: new in versus closed applications
| Week commencing |
New in |
Closed applications |
Total cases in progress |
| 11 May |
11 |
3 |
165 |
| 18 May |
12 |
13 |
164 |
| 25 May |
6 |
12 |
158 |
| 1 June |
7 |
15 |
150 |
| 8 June |
8 |
6 |
152 |
| 15 Jun |
14 |
11 |
155 |
| 22 Jun |
12 |
9 |
158 |
| 29 Jun |
8 |
2 |
164 |
| 6 Jul |
19 |
8 |
175 |
| 13 Jul |
20 |
7 |
188 |
| 20 Jul |
9 |
11 |
186 |
| 27 Jul |
14 |
19 |
181 |
| Application type |
Live major change requests |
New in |
Closed |
Median weeks to close |
| New HRBs and conversions |
76 |
83 |
68 |
7 |
| Remediation |
21 |
19 |
28 |
14 |
|
NHS applications |
60 |
27 |
15 |
8 |
|
HRB internal works |
21 |
9 |
1 |
20 |
-
BSR recognises that the timely processing of major change requests during build is vital to ensure construction can continue.
- There are currently 181 live major change requests, with 112 having been closed.
- The median closure time for new build projects is currently at 7 weeks, just one week more than the statutory target.
- Transitional major change requests make up the remaining 3 of the 181 not shown in the in-build data tables, with 2 new in and 4 closed.
Gateway 3 applications
Data as of 1 August 2026.
Gateway 3 applications: new in versus closed applications
| Week commencing |
New in |
Closed applications |
Total cases in progress |
| 11 May |
5 |
4 |
123 |
| 18 May |
5 |
4 |
122 |
| 25 May |
8 |
2 |
128 |
| 1 Jun |
4 |
1 |
128 |
| 8 Jun |
2 |
9 |
126 |
| 15 Jun |
7 |
2 |
131 |
| 22 Jun |
4 |
3 |
134 |
| 29 Jun |
3 |
2 |
128 |
| 6 Jul |
5 |
1 |
131 |
| 13 Jul |
1 |
0 |
129 |
| 20 Jul |
1 |
0 |
128 |
| 27 Jul |
0 |
0 |
127 |
| Application type |
In progress |
Units |
Approvals |
New in |
| New HRBs and conversions |
0 |
0 |
0 |
0 |
| Remediation |
5 |
655 |
1 |
3 |
|
NHS internal works |
81 |
NA |
13 |
30 |
|
HRB internal works |
15 |
NA |
4 |
7 |
- While no new build projects that have passed through gateway 2 have reached gateway 3, a significant number of internal refurbishment projects have already passed through gateway 2.
- Of the 319 gateway 3 applications received, 235 are internal refurbishments. Most the remaining applications are transitional cases (47) and NHS internal refurbishments (23).
- Over the past 12 weeks, 29 gateway 3 applications have been determined with an approval rate of 72% and a median determination time of 16 weeks. The quickest determination was 8 weeks. This is an important area for BSR, particularly for new build projects, and we expect determination times to reduce as new processes are introduced and more resource is found.