All data is correct as of 31 August 2026 and provided by the Building Safety Regulator (BSR).
Introduction
As in previous months, this BSR dataset includes information relating to gateway 2 performance, with London performance reported separately.
It also includes data on internal and external resource usage and gateway 3 performance.
National Health Service (NHS) applications are included as a separate category.
Detailed information on the number of major change requests and their processing times is also included. Timely resolution of these requests during construction is essential for work to continue.
Recent trends
There has been an increase in gateway 2 applications. This could be because of the building safety levy, which comes into effect in October 2026. BSR has a mitigation plan in place and will continue to monitor the rate of new applications.
BSR’s growing inspection programme has found a small number of examples where building work has not followed agreed designs and has required some remedial work. BSR will monitor this closely and take action where appropriate to help make sure that buildings are constructed in line with safe designs.
Gateway 2: headline numbers for June to August 2026
| Status |
New higher-risk buildings (HRBs) and conversions |
External remediation |
| Cases in progress |
147 |
327 |
| Invalid or withdrawn |
5 |
20 |
| Decisions made |
50 |
118 |
| New in |
63 |
109 |
| Approval rate |
92% |
89% |
| Median approval time |
22 weeks |
33 weeks |
| Units approved |
9,362 |
8,667 |
- August 2026 marks 12 months since the Innovation Unit (IU) was set up to deal exclusively with new build higher-risk building (HRB) applications.
- At that point, the median approval time for new builds was 43 weeks, with an approval rate of 39%.
- The median approval time is now 22 weeks, with an approval rate of 92%.
- Over the same period, performance for remediation applications improved significantly. Approval times fell from 43 weeks to 33 weeks, and approval rates increased from 47% to 89%.
- There was a steady increase in new build applications in August, reaching 34. BSR expects this number to increase in September due to the introduction of the building safety levy on 1 October 2026.
Gateway 2: headline numbers for June to August 2026 – internal works and NHS
| Status |
HRB internal works |
NHS internal works |
| Cases in progress |
1,082 |
32 |
| Invalid or withdrawn |
141 |
8 |
| Decisions made |
143 |
22 |
| New in |
457 |
30 |
| Approval rate |
78% |
82% |
| Median approval time |
32 weeks |
22 weeks |
-
NHS applications continue as a separate category. They were previously reported within the HRB internal works dataset.
- These can include a range of building work in hospitals, from maintenance to new hospital facilities.
-
BSR has been working closely with the NHS to support the specialist nature of its applications.
- This has started to show results, with some recent approvals coming in at the statutory 8-week timescale.
- The median approval time for NHS applications submitted in 2026 has reduced to 13 weeks.
- The median approval time for HRB internal works applications submitted in 2026 has reduced to 16 weeks.
- Overall median approval times are higher as BSR continues to close older applications from 2025.
All application categories
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 8 June |
55 |
49 |
1,515 |
| 15 June |
55 |
49 |
1,521 |
| 22 June |
53 |
48 |
1,526 |
| 29 June |
55 |
37 |
1,544 |
| 6 July |
51 |
39 |
1,556 |
| 13 July |
46 |
59 |
1,543 |
| 20 July |
47 |
39 |
1,551 |
| 27 July |
56 |
53 |
1,554 |
| 3 August |
62 |
34 |
1,582 |
| 10 August |
48 |
23 |
1,607 |
| 17 August |
70 |
47 |
1,630 |
| 24 August |
80 |
56 |
1,654 |
- There are currently 1,654 gateway 2 applications in progress. This is an increase of more than 100 in August. BSR will monitor whether this increase continues.
- These include new build, remediation, internal refurbishment and NHS applications, which are explained in more detail later.
- Transitional cases are also included. These are projects that revert to BSR when the building control body that was originally overseeing the project stops trading.
- These projects commenced under the previous building control regime and are generally more complicated to progress because much of the evidence now expected at gateway 2 is not available.
- There are currently 66 transitional cases in progress at gateway 2.
New HRBs and conversions (national)
New HRBs and conversions: new in versus closed decisions (national)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 8 June |
2 |
3 |
138 |
| 15 June |
4 |
5 |
137 |
| 22 June |
4 |
4 |
137 |
| 29 June |
2 |
5 |
134 |
| 6 July |
2 |
2 |
134 |
| 13 July |
7 |
9 |
132 |
| 20 July |
4 |
4 |
132 |
| 27 July |
4 |
10 |
126 |
| 3 August |
9 |
2 |
133 |
| 10 August |
6 |
4 |
135 |
| 17 August |
12 |
3 |
144 |
| 24 August |
7 |
4 |
147 |
| Description |
Total |
| New in |
63 |
| In progress |
147 |
| Units approved |
9,362 |
| Units in progress |
32,691 |
New HRBs and conversions: percentages and weeks taken (national)
In the period, there were:
- 50 decisions made
- 5 invalid or withdrawn applications
- 33 complex cases in progress with a median approval time of 33 weeks
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
8% |
8 |
| Approval rate |
92% |
22 |
- Of 63 applications received over the past 12 weeks, 4 applications were invalidated and one was withdrawn. Of the 50 decisions made, 46 were approvals and 4 were rejections.
- The 12-week rolling approval rate, excluding invalidations and withdrawals, has risen to 92%, with a median approval time of 22 weeks.
- Complex cases are now tracked separately. The final decision is included in the rejection or approval totals, and their median approval time is 33 weeks.
-
BSR continues to work closely with industry on a shared understanding of compliance as it works to reduce the number of complex cases in the system.
- The overall combined total is 147. This has increased from 131 at the end of July 2026.
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 8 June |
9 |
12 |
353 |
| 15 June |
7 |
15 |
345 |
| 22 June |
11 |
9 |
347 |
| 29 June |
16 |
12 |
351 |
| 6 July |
8 |
13 |
346 |
| 13 July |
5 |
16 |
335 |
| 20 July |
9 |
7 |
337 |
| 27 July |
10 |
11 |
336 |
| 3 August |
9 |
9 |
336 |
| 10 August |
14 |
5 |
345 |
| 17 August |
6 |
13 |
338 |
| 24 August |
5 |
16 |
327 |
| Description |
Total |
| New in |
109 |
| In progress |
327 |
| Units approved |
8,667 |
| Units in progress |
28,274 |
In the period, there were:
- 118 decisions made
- 20 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
11% |
44 |
| Approvals |
89% |
33 |
- The rolling 12-week approval rate has increased to 89%, with the median approval time falling to 33 weeks. This is a positive trend, but remains above target because older cases that have been in the system for some time are included.
- 12 legacy applications made in 2024 remain, down from 42 at the start of 2026.
-
BSR continues to work closely with the sector to help applicants improve the quality of applications.
- Applications submitted between October and December 2025 are moving faster through the system than earlier applications.
- The average approval time still appears high because it includes older applications from 2025 that are still being cleared.
- 2026 approval rates already exceed the 75% target at 89%
HRB internal works (national)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 8 June |
37 |
27 |
919 |
| 15 June |
38 |
24 |
933 |
| 22 June |
34 |
34 |
933 |
| 29 June |
33 |
18 |
948 |
| 6 July |
36 |
21 |
963 |
| 13 July |
28 |
25 |
966 |
| 20 July |
30 |
21 |
975 |
| 27 July |
40 |
28 |
987 |
| 3 August |
40 |
20 |
1,007 |
| 10 August |
25 |
11 |
1,021 |
| 17 August |
50 |
22 |
1,049 |
| 24 August |
66 |
33 |
1,082 |
| Description |
Total |
| New in |
457 |
| In progress |
1,082 |
Percentages and weeks taken (national)
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
22% |
24 |
| Approval rate |
78% |
32 |
- The approval rate for internal refurbishment works in category A and B is currently 78%, with a median determination time for approvals of 32 weeks.
- New applications have been received at an average rate of 38 per week over the past 12 weeks. The weekly rate was higher in August. BSR expects this increase to reduce as determination times reduce.
- The overall combined total is an expected 1,082, having increased over the past 12 weeks.
-
HRB internal work determinations over the past 12 weeks account for around 43% of all gateway 2 decisions. These applications include all internal refurbishment works except NHS applications.
NHS internal works (national)
NHS internal works: new in versus closed decisions (national)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 8 June |
1 |
3 |
30 |
| 15 June |
5 |
2 |
33 |
| 22 June |
3 |
1 |
35 |
| 29 June |
2 |
0 |
37 |
| 6 July |
2 |
2 |
37 |
| 13 July |
5 |
4 |
38 |
| 20 July |
2 |
5 |
35 |
| 27 July |
2 |
1 |
36 |
| 3 August |
3 |
3 |
36 |
| 10 August |
2 |
2 |
36 |
| 17 August |
2 |
6 |
32 |
| 24 August |
1 |
1 |
32 |
| Description |
Total |
| New in |
30 |
| In progress |
32 |
NHS internal works: percentages and weeks taken (national)
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
18% |
15 |
| Approval rate |
82% |
22 |
-
NHS internal works have now been split from HRB internal works.
- The approval rate for NHS internal refurbishment is currently 82%.
- The median determination time for approvals is 22 weeks.
- New applications have been received at an average rate of 2 per week over the past 12 weeks.
Gateway 2: regional distribution
Data as of 31 August 2026.
Regional gateway 2 applications (London)
| Region |
New HRBs and conversions |
External remediation |
HRB internal works |
Transitional |
Total |
| London |
96 |
182 |
734 |
0 |
0 |
| Rest of England |
40 |
144 |
328 |
30 |
560 |
Regional gateway 2 applications (rest of England)
| Region |
New HRBs and conversions |
External remediation |
HRB internal works |
NHS |
Transitional |
| East |
0 |
18 |
43 |
1 |
1 |
| East Midlands |
0 |
9 |
25 |
2 |
2 |
| North East |
0 |
9 |
35 |
4 |
2 |
| North West |
17 |
42 |
36 |
1 |
13 |
| South East |
6 |
31 |
46 |
3 |
3 |
| South West |
6 |
22 |
76 |
3 |
6 |
| West Midlands |
6 |
3 |
29 |
1 |
1 |
| Yorkshire and The Humber |
4 |
10 |
38 |
3 |
3 |
New HRBs and conversions (London)
New HRBs and conversions: new in versus closed decisions (London)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 8 June |
1 |
2 |
90 |
| 15 June |
1 |
4 |
87 |
| 22 June |
3 |
2 |
88 |
| 29 June |
2 |
3 |
87 |
| 6 July |
0 |
2 |
85 |
| 13 July |
3 |
3 |
85 |
| 20 July |
2 |
3 |
84 |
| 27 July |
2 |
7 |
79 |
| 3 August |
6 |
1 |
84 |
| 10 August |
6 |
1 |
89 |
| 17 August |
10 |
3 |
96 |
| 24 August |
2 |
2 |
96 |
| Description |
Total |
| New in |
38 |
| In progress |
96 |
| Units approved |
4,477 |
| Units in progress |
20,046 |
New HRBs and conversions: percentages and weeks taken (London)
| Description |
Percentage |
Weeks taken (median) |
| Approval rate |
90% |
23 |
| Rejection rate |
10% |
6 |
- Around 65% of in-progress new build applications are in London.
- This represents around 61% of the overall new build residential units handled by BSR.
- Of the 50 new build decisions made in the last 12 weeks, 31 are in London.
- The London approval rate is 90%. This reflects significant work to resolve outstanding complex cases.
- The approval time for non-complex cases is 23 weeks, slightly above the national average.
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 8 June |
4 |
4 |
200 |
| 15 June |
4 |
9 |
195 |
| 22 June |
7 |
5 |
197 |
| 29 June |
4 |
3 |
198 |
| 6 July |
3 |
6 |
195 |
| 13 July |
4 |
7 |
192 |
| 20 July |
4 |
6 |
190 |
| 27 July |
2 |
6 |
186 |
| 3 August |
2 |
4 |
184 |
| 10 August |
6 |
3 |
187 |
| 17 August |
3 |
4 |
186 |
| 24 August |
4 |
8 |
182 |
| Description |
Total |
| New in |
47 |
| In progress |
182 |
| Units approved |
3,936 |
| Units in progress |
15,395 |
| Description |
Percentage |
Weeks taken (median) |
| Approval rate |
96% |
32 |
| Rejection rate |
4% |
18 |
- Open remediation cases in London have dropped over the period from 200 to 182.
- Progress has been made since the announcement of the BSR remediation improvement plan in April 2026. There are now 12 legacy applications from 2024 remaining, down from 42 at the start of 2026.
- The median approval time based on the rolling total reflects work to close older applications from 2024 and 2025. These applications continue to affect overall median approval times.
- Applications submitted in 2026 are being determined much more quickly.
- London’s approval rate of 96% is slightly higher than the national rate.
HRB internal works (London)
HRB internal works: new in versus closed decisions (London)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 8 June |
27 |
14 |
599 |
| 15 June |
32 |
18 |
613 |
| 22 June |
22 |
21 |
614 |
| 29 June |
22 |
9 |
627 |
| 6 July |
25 |
11 |
641 |
| 13 July |
18 |
19 |
640 |
| 20 July |
22 |
13 |
649 |
| 27 July |
33 |
22 |
660 |
| 3 August |
25 |
16 |
669 |
| 10 August |
23 |
8 |
684 |
| 17 August |
30 |
15 |
699 |
| 24 August |
52 |
17 |
734 |
| Description |
Total |
| New in |
331 |
| In progress |
734 |
HRB internal works: percentages and weeks taken (London)
| Description |
Percentage |
Weeks taken (median) |
| Approval rate |
78% |
32 |
| Rejection rate |
22% |
25 |
- The approval rate for internal refurbishment works in category A and B is currently 78%, with a median determination time for approvals of 32 weeks. This is very similar to the national average.
- The overall combined total is less than the expected total of 850 to 900. It is currently 734, having increased over the past 12 weeks.
-
HRB internal work determinations over the past 12 weeks account for around 46% of gateway 2 decisions. These applications include all internal refurbishment works except NHS applications.
NHS internal works (London)
NHS internal works: new in versus closed decisions (London)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 8 June |
0 |
1 |
12 |
| 15 June |
3 |
1 |
14 |
| 22 June |
0 |
0 |
14 |
| 29 June |
2 |
0 |
16 |
| 6 July |
2 |
0 |
18 |
| 13 July |
1 |
2 |
17 |
| 20 July |
0 |
2 |
15 |
| 27 July |
0 |
0 |
15 |
| 3 August |
0 |
0 |
15 |
| 10 August |
2 |
0 |
17 |
| 17 August |
0 |
4 |
13 |
| 24 August |
0 |
0 |
13 |
| Description |
Total |
| New in |
10 |
| In progress |
13 |
NHS internal works: percentages and weeks taken (London)
| Description |
Percentage |
Weeks taken (median) |
| Approval rate |
78% |
33 |
| Rejection rate |
22% |
14 |
-
NHS internal works have now been split from HRB internal works.
- The approval rate for NHS internal refurbishment works is currently 78%, with a median determination time for approvals of 33 weeks. This is slightly higher than the national average.
Building control resources: people working on building control applications
| Week commencing |
Internal resources |
External resources |
Total resources |
| 8 June |
110 |
281 |
391 |
| 15 June |
115 |
262 |
377 |
| 22 June |
122 |
256 |
378 |
| 29 June |
134 |
253 |
387 |
| 6 July |
142 |
255 |
397 |
| 13 July |
149 |
262 |
411 |
| 20 July |
145 |
264 |
409 |
| 27 July |
142 |
241 |
383 |
| 3 August |
137 |
236 |
373 |
| 10 August |
139 |
233 |
372 |
| 17 August |
138 |
223 |
361 |
| 24 August |
135 |
208 |
343 |
| Description |
Total |
| Internal resources |
177 |
| External resources |
508 |
| Integrated resources |
64 |
Building control resources: resource breakdown
Internal resources
| Description |
Total |
| Regulatory leads |
101 |
| Principal regulatory leads |
14 |
| Case officers |
58 |
| Case officer managers |
4 |
External resources
| Description |
Total |
| Registered building inspectors (RBIs) |
240 |
| Fire service professionals |
106 |
| Structural engineers |
127 |
| Specialists |
35 |
Integrated resources
| Description |
Total |
| Registered building inspectors (RBIs) |
36 |
| Fire service professionals |
8 |
| Structural engineers |
20 |
- Sufficient internal, external and integrated resources are essential for BSR to meet demand. BSR has grown its internal regulatory team by 25 over the past 3 months and is continuing to recruit over the next 6 to 12 months.
-
BSR is also growing its integrated resource teams to meet demand.
Building control integrated resources
BSR has several specialist resources working as part of an integrated workforce within the new build and remediation teams. BSR is growing this capacity to meet demand and reduce processing times.
| Resource |
FTE as of 31 July |
Headcount as of 31 July |
August forecast (FTE) |
September forecast (FTE) |
October forecast (FTE) |
| Registered building inspectors |
23.3 |
36 |
25.3 |
29.3 |
34.3 |
| Structural engineers |
20 |
22 |
20 |
21 |
25 |
| Fire service professionals and engineers |
6.6 |
7 |
6.6 |
6.6 |
11.6 |
Full-time equivalent (FTE) is an aggregated total of staff availability, as some people are available fewer than 5 days per week.
In build: major changes from June to August 2026
Data as of 31 August 2026.
In build: new in versus closed applications
| Week commencing |
New in |
Closed applications |
Total cases in progress |
| 8 June |
8 |
6 |
153 |
| 15 June |
14 |
11 |
156 |
| 22 June |
12 |
9 |
159 |
| 29 June |
8 |
2 |
165 |
| 6 July |
18 |
8 |
175 |
| 13 July |
20 |
7 |
188 |
| 20 July |
9 |
11 |
186 |
| 27 July |
14 |
19 |
181 |
| 3 August |
9 |
11 |
179 |
| 10 August |
17 |
9 |
187 |
| 17 August |
18 |
23 |
182 |
| 24 August |
9 |
7 |
184 |
| Application type |
Major change requests in progress |
New in |
Closed |
Median weeks to close |
| New HRBs and conversions |
78 |
99 |
77 |
7 |
| External remediations |
11 |
15 |
24 |
10 |
|
HRB internal works |
67 |
29 |
17 |
9 |
|
NHS applications |
25 |
11 |
1 |
20 |
-
BSR recognises that the timely processing of major change requests during construction is vital to make sure construction can continue.
- There are currently 184 major change requests in progress. A total of 123 requests have been closed in the period, including 119 shown in the data tables and 4 transitional requests.
- The median closure time for new build projects is currently 7 weeks, one week more than the statutory target.
- Transitional major change requests make up the remaining 3 of the 184 not shown in the data tables, with 2 new in and 4 closed.
Gateway 3 applications from June to August 2026
Data as of 31 August 2026.
Gateway 3 applications: new in versus closed applications
| Week commencing |
New in |
Closed applications |
Total cases in progress |
| 8 June |
3 |
4 |
126 |
| 15 June |
7 |
2 |
131 |
| 22 June |
4 |
1 |
134 |
| 29 June |
3 |
9 |
128 |
| 6 July |
7 |
2 |
133 |
| 13 July |
3 |
3 |
133 |
| 20 July |
3 |
2 |
134 |
| 27 July |
3 |
1 |
136 |
| 3 August |
7 |
0 |
143 |
| 10 August |
4 |
0 |
147 |
| 17 August |
8 |
1 |
154 |
| 24 August |
3 |
1 |
156 |
| Application type |
In progress |
Units |
Approvals |
New in |
| New HRBs and conversions |
0 |
0 |
0 |
0 |
| External remediation |
8 |
972 |
0 |
3 |
|
NHS internal works |
15 |
Not applicable |
4 |
5 |
|
HRB internal works |
105 |
Not applicable |
9 |
45 |
- No new build projects that have passed through gateway 2 have reached gateway 3.
- The inspection regime for new build projects has identified a small amount of building work that deviates from designs agreed at gateway 2.
- Of the 346 gateway 3 applications received, 260 are internal refurbishments. Most of the remainder are transitional cases, at 45, and NHS internal refurbishments, at 23.
- Over the past 12 weeks, 16 gateway 3 applications have been determined, with an approval rate of 88% and a median determination time of 20 weeks. The quickest determination was 7 weeks. This is an important area for BSR, particularly for new build projects, and BSR expects determination times to reduce as new processes are introduced and more resource is found.