Building Safety Regulator building control approval application data June to August 2026

Updated 15 September 2026

Applies to England

All data is correct as of 31 August 2026 and provided by the Building Safety Regulator (BSR).

Introduction

As in previous months, this BSR dataset includes information relating to gateway 2 performance, with London performance reported separately.

It also includes data on internal and external resource usage and gateway 3 performance.

National Health Service (NHS) applications are included as a separate category.

Detailed information on the number of major change requests and their processing times is also included. Timely resolution of these requests during construction is essential for work to continue.

There has been an increase in gateway 2 applications. This could be because of the building safety levy, which comes into effect in October 2026. BSR has a mitigation plan in place and will continue to monitor the rate of new applications.

BSR’s growing inspection programme has found a small number of examples where building work has not followed agreed designs and has required some remedial work. BSR will monitor this closely and take action where appropriate to help make sure that buildings are constructed in line with safe designs.

Gateway 2: headline numbers for June to August 2026

Status New higher-risk buildings (HRBs) and conversions External remediation
Cases in progress 147 327
Invalid or withdrawn 5 20
Decisions made 50 118
New in 63 109
Approval rate 92% 89%
Median approval time 22 weeks 33 weeks
Units approved 9,362 8,667

Commentary

  • August 2026 marks 12 months since the Innovation Unit (IU) was set up to deal exclusively with new build higher-risk building (HRB) applications.
  • At that point, the median approval time for new builds was 43 weeks, with an approval rate of 39%.
  • The median approval time is now 22 weeks, with an approval rate of 92%.
  • Over the same period, performance for remediation applications improved significantly. Approval times fell from 43 weeks to 33 weeks, and approval rates increased from 47% to 89%.
  • There was a steady increase in new build applications in August, reaching 34. BSR expects this number to increase in September due to the introduction of the building safety levy on 1 October 2026.

Gateway 2: headline numbers for June to August 2026 – internal works and NHS

Status HRB internal works NHS internal works
Cases in progress 1,082 32
Invalid or withdrawn 141 8
Decisions made 143 22
New in 457 30
Approval rate 78% 82%
Median approval time 32 weeks 22 weeks

Commentary

  • NHS applications continue as a separate category. They were previously reported within the HRB internal works dataset.
  • These can include a range of building work in hospitals, from maintenance to new hospital facilities.
  • BSR has been working closely with the NHS to support the specialist nature of its applications.
  • This has started to show results, with some recent approvals coming in at the statutory 8-week timescale.
  • The median approval time for NHS applications submitted in 2026 has reduced to 13 weeks.
  • The median approval time for HRB internal works applications submitted in 2026 has reduced to 16 weeks.
  • Overall median approval times are higher as BSR continues to close older applications from 2025.

All application categories

Week commencing New in Closed decisions Total cases in progress
8 June 55 49 1,515
15 June 55 49 1,521
22 June 53 48 1,526
29 June 55 37 1,544
6 July 51 39 1,556
13 July 46 59 1,543
20 July 47 39 1,551
27 July 56 53 1,554
3 August 62 34 1,582
10 August 48 23 1,607
17 August 70 47 1,630
24 August 80 56 1,654

Commentary

  • There are currently 1,654 gateway 2 applications in progress. This is an increase of more than 100 in August. BSR will monitor whether this increase continues.
  • These include new build, remediation, internal refurbishment and NHS applications, which are explained in more detail later.
  • Transitional cases are also included. These are projects that revert to BSR when the building control body that was originally overseeing the project stops trading.
  • These projects commenced under the previous building control regime and are generally more complicated to progress because much of the evidence now expected at gateway 2 is not available.
  • There are currently 66 transitional cases in progress at gateway 2.

New HRBs and conversions (national)

New HRBs and conversions: new in versus closed decisions (national)

Week commencing New in Closed decisions Total cases in progress
8 June 2 3 138
15 June 4 5 137
22 June 4 4 137
29 June 2 5 134
6 July 2 2 134
13 July 7 9 132
20 July 4 4 132
27 July 4 10 126
3 August 9 2 133
10 August 6 4 135
17 August 12 3 144
24 August 7 4 147

New HRBs and conversions: performance (national)

Description Total
New in 63
In progress 147
Units approved 9,362
Units in progress 32,691

New HRBs and conversions: percentages and weeks taken (national)

In the period, there were:

  • 50 decisions made
  • 5 invalid or withdrawn applications
  • 33 complex cases in progress with a median approval time of 33 weeks
Description Percentage Weeks taken (median)
Rejection rate 8% 8
Approval rate 92% 22

Commentary

  • Of 63 applications received over the past 12 weeks, 4 applications were invalidated and one was withdrawn. Of the 50 decisions made, 46 were approvals and 4 were rejections.
  • The 12-week rolling approval rate, excluding invalidations and withdrawals, has risen to 92%, with a median approval time of 22 weeks.
  • Complex cases are now tracked separately. The final decision is included in the rejection or approval totals, and their median approval time is 33 weeks.
  • BSR continues to work closely with industry on a shared understanding of compliance as it works to reduce the number of complex cases in the system.
  • The overall combined total is 147. This has increased from 131 at the end of July 2026.

External remediation (national)

External remediation: new in versus closed decisions (national)

Week commencing New in Closed decisions Total cases in progress
8 June 9 12 353
15 June 7 15 345
22 June 11 9 347
29 June 16 12 351
6 July 8 13 346
13 July 5 16 335
20 July 9 7 337
27 July 10 11 336
3 August 9 9 336
10 August 14 5 345
17 August 6 13 338
24 August 5 16 327

External remediation: performance (national)

Description Total
New in 109
In progress 327
Units approved 8,667
Units in progress 28,274

External remediation: percentages and weeks taken (national)

In the period, there were:

  • 118 decisions made
  • 20 invalid or withdrawn applications
Description Percentage Weeks taken (median)
Rejection rate 11% 44
Approvals 89% 33

Commentary

  • The rolling 12-week approval rate has increased to 89%, with the median approval time falling to 33 weeks. This is a positive trend, but remains above target because older cases that have been in the system for some time are included.
  • 12 legacy applications made in 2024 remain, down from 42 at the start of 2026.
  • BSR continues to work closely with the sector to help applicants improve the quality of applications.
  • Applications submitted between October and December 2025 are moving faster through the system than earlier applications.
  • The average approval time still appears high because it includes older applications from 2025 that are still being cleared.
  • 2026 approval rates already exceed the 75% target at 89%

HRB internal works (national)

Week commencing New in Closed decisions Total cases in progress
8 June 37 27 919
15 June 38 24 933
22 June 34 34 933
29 June 33 18 948
6 July 36 21 963
13 July 28 25 966
20 July 30 21 975
27 July 40 28 987
3 August 40 20 1,007
10 August 25 11 1,021
17 August 50 22 1,049
24 August 66 33 1,082

HRB internal works: performance (national)

Description Total
New in 457
In progress 1,082

Percentages and weeks taken (national)

Description Percentage Weeks taken (median)
Rejection rate 22% 24
Approval rate 78% 32

Commentary

  • The approval rate for internal refurbishment works in category A and B is currently 78%, with a median determination time for approvals of 32 weeks.
  • New applications have been received at an average rate of 38 per week over the past 12 weeks. The weekly rate was higher in August. BSR expects this increase to reduce as determination times reduce.
  • The overall combined total is an expected 1,082, having increased over the past 12 weeks.
  • HRB internal work determinations over the past 12 weeks account for around 43% of all gateway 2 decisions. These applications include all internal refurbishment works except NHS applications.

NHS internal works (national)

NHS internal works: new in versus closed decisions (national)

Week commencing New in Closed decisions Total cases in progress
8 June 1 3 30
15 June 5 2 33
22 June 3 1 35
29 June 2 0 37
6 July 2 2 37
13 July 5 4 38
20 July 2 5 35
27 July 2 1 36
3 August 3 3 36
10 August 2 2 36
17 August 2 6 32
24 August 1 1 32

NHS internal works: performance (national)

Description Total
New in 30
In progress 32

NHS internal works: percentages and weeks taken (national)

Description Percentage Weeks taken (median)
Rejection rate 18% 15
Approval rate 82% 22

Commentary

  • NHS internal works have now been split from HRB internal works.
  • The approval rate for NHS internal refurbishment is currently 82%.
  • The median determination time for approvals is 22 weeks.
  • New applications have been received at an average rate of 2 per week over the past 12 weeks.

Gateway 2: regional distribution

Data as of 31 August 2026.​

Regional gateway 2 applications (London)

Region New HRBs and conversions External remediation HRB internal works Transitional Total
London 96 182 734 0 0
Rest of England 40 144 328 30 560

Regional gateway 2 applications (rest of England)

Region New HRBs and conversions External remediation HRB internal works NHS Transitional
East 0 18 43 1 1
East Midlands 0 9 25 2 2
North East 0 9 35 4 2
North West 17 42 36 1 13
South East 6 31 46 3 3
South West 6 22 76 3 6
West Midlands 6 3 29 1 1
Yorkshire and The Humber 4 10 38 3 3

New HRBs and conversions (London)

New HRBs and conversions: new in versus closed decisions (London)

Week commencing New in Closed decisions Total cases in progress
8 June 1 2 90
15 June 1 4 87
22 June 3 2 88
29 June 2 3 87
6 July 0 2 85
13 July 3 3 85
20 July 2 3 84
27 July 2 7 79
3 August 6 1 84
10 August 6 1 89
17 August 10 3 96
24 August 2 2 96

New HRBs and conversions: performance (London)

Description Total
New in 38
In progress 96
Units approved 4,477
Units in progress 20,046

New HRBs and conversions: percentages and weeks taken (London)

Description Percentage Weeks taken (median)
Approval rate 90% 23
Rejection rate 10% 6

Commentary

  • Around 65% of in-progress new build applications are in London.
  • This represents around 61% of the overall new build residential units handled by BSR.
  • Of the 50 new build decisions made in the last 12 weeks, 31 are in London.
  • The London approval rate is 90%. This reflects significant work to resolve outstanding complex cases.
  • The approval time for non-complex cases is 23 weeks, slightly above the national average.

External remediation (London)

Week commencing New in Closed decisions Total cases in progress
8 June 4 4 200
15 June 4 9 195
22 June 7 5 197
29 June 4 3 198
6 July 3 6 195
13 July 4 7 192
20 July 4 6 190
27 July 2 6 186
3 August 2 4 184
10 August 6 3 187
17 August 3 4 186
24 August 4 8 182

External remediation: performance (London)

Description Total
New in 47
In progress 182
Units approved 3,936
Units in progress 15,395

External remediation: percentages and weeks taken (London)

Description Percentage Weeks taken (median)
Approval rate 96% 32
Rejection rate 4% 18

Commentary

  • Open remediation cases in London have dropped over the period from 200 to 182.
  • Progress has been made since the announcement of the BSR remediation improvement plan in April 2026. There are now 12 legacy applications from 2024 remaining, down from 42 at the start of 2026.
  • The median approval time based on the rolling total reflects work to close older applications from 2024 and 2025. These applications continue to affect overall median approval times.
  • Applications submitted in 2026 are being determined much more quickly.
  • London’s approval rate of 96% is slightly higher than the national rate.

HRB internal works (London)

HRB internal works: new in versus closed decisions (London)

Week commencing New in Closed decisions Total cases in progress
8 June 27 14 599
15 June 32 18 613
22 June 22 21 614
29 June 22 9 627
6 July 25 11 641
13 July 18 19 640
20 July 22 13 649
27 July 33 22 660
3 August 25 16 669
10 August 23 8 684
17 August 30 15 699
24 August 52 17 734

HRB internal works: performance (London)

Description Total
New in 331
In progress 734

HRB internal works: percentages and weeks taken (London)

Description Percentage Weeks taken (median)
Approval rate 78% 32
Rejection rate 22% 25

Commentary

  • The approval rate for internal refurbishment works in category A and B is currently 78%, with a median determination time for approvals of 32 weeks. This is very similar to the national average.
  • The overall combined total is less than the expected total of 850 to 900. It is currently 734, having increased over the past 12 weeks.
  • HRB internal work determinations over the past 12 weeks account for around 46% of gateway 2 decisions. These applications include all internal refurbishment works except NHS applications.

NHS internal works (London)

NHS internal works: new in versus closed decisions (London)

Week commencing New in Closed decisions Total cases in progress
8 June 0 1 12
15 June 3 1 14
22 June 0 0 14
29 June 2 0 16
6 July 2 0 18
13 July 1 2 17
20 July 0 2 15
27 July 0 0 15
3 August 0 0 15
10 August 2 0 17
17 August 0 4 13
24 August 0 0 13

NHS internal works: performance (London)

Description Total
New in 10
In progress 13

NHS internal works: percentages and weeks taken (London)

Description Percentage Weeks taken (median)
Approval rate 78% 33
Rejection rate 22% 14

Commentary

  • NHS internal works have now been split from HRB internal works.
  • The approval rate for NHS internal refurbishment works is currently 78%, with a median determination time for approvals of 33 weeks. This is slightly higher than the national average.

Building control resources: people working on building control applications

Week commencing Internal resources External resources Total resources
8 June 110 281 391
15 June 115 262 377
22 June 122 256 378
29 June 134 253 387
6 July 142 255 397
13 July 149 262 411
20 July 145 264 409
27 July 142 241 383
3 August 137 236 373
10 August 139 233 372
17 August 138 223 361
24 August 135 208 343

Building control resources: performance

Description Total
Internal resources 177
External resources 508
Integrated resources 64

Building control resources: resource breakdown

Internal resources

Description Total
Regulatory leads 101
Principal regulatory leads 14
Case officers 58
Case officer managers 4

External resources

Description Total
Registered building inspectors (RBIs) 240
Fire service professionals 106
Structural engineers 127
Specialists 35

Integrated resources

Description Total
Registered building inspectors (RBIs) 36
Fire service professionals 8
Structural engineers 20

Commentary

  • Sufficient internal, external and integrated resources are essential for BSR to meet demand. BSR has grown its internal regulatory team by 25 over the past 3 months and is continuing to recruit over the next 6 to 12 months.
  • BSR is also growing its integrated resource teams to meet demand.

Building control integrated resources

BSR has several specialist resources working as part of an integrated workforce within the new build and remediation teams. BSR is growing this capacity to meet demand and reduce processing times.

Resource FTE as of 31 July Headcount as of 31 July August forecast (FTE) September forecast (FTE) October forecast (FTE)
Registered building inspectors 23.3 36 25.3 29.3 34.3
Structural engineers 20 22 20 21 25
Fire service professionals and engineers 6.6 7 6.6 6.6 11.6

Full-time equivalent (FTE) is an aggregated total of staff availability, as some people are available fewer than 5 days per week.

In build: major changes from June to August 2026

Data as of 31 August 2026.

In build: new in versus closed applications

Week commencing New in Closed applications Total cases in progress
8 June 8 6 153
15 June 14 11 156
22 June 12 9 159
29 June 8 2 165
6 July 18 8 175
13 July 20 7 188
20 July 9 11 186
27 July 14 19 181
3 August 9 11 179
10 August 17 9 187
17 August 18 23 182
24 August 9 7 184
Application type Major change requests in progress New in Closed Median weeks to close
New HRBs and conversions 78 99 77 7
External remediations 11 15 24 10
HRB internal works 67 29 17 9
NHS applications 25 11 1 20

Commentary

  • BSR recognises that the timely processing of major change requests during construction is vital to make sure construction can continue.
  • There are currently 184 major change requests in progress. A total of 123 requests have been closed in the period, including 119 shown in the data tables and 4 transitional requests.
  • The median closure time for new build projects is currently 7 weeks, one week more than the statutory target.
  • Transitional major change requests make up the remaining 3 of the 184 not shown in the data tables, with 2 new in and 4 closed.

Gateway 3 applications from June to August 2026

Data as of 31 August 2026.

Gateway 3 applications: new in versus closed applications

Week commencing New in Closed applications Total cases in progress
8 June 3 4 126
15 June 7 2 131
22 June 4 1 134
29 June 3 9 128
6 July 7 2 133
13 July 3 3 133
20 July 3 2 134
27 July 3 1 136
3 August 7 0 143
10 August 4 0 147
17 August 8 1 154
24 August 3 1 156

Gateway 3 applications: performance

Application type In progress Units Approvals New in
New HRBs and conversions 0 0 0 0
External remediation 8 972 0 3
NHS internal works 15 Not applicable 4 5
HRB internal works 105 Not applicable 9 45

Commentary

  • No new build projects that have passed through gateway 2 have reached gateway 3.
  • The inspection regime for new build projects has identified a small amount of building work that deviates from designs agreed at gateway 2.
  • Of the 346 gateway 3 applications received, 260 are internal refurbishments. Most of the remainder are transitional cases, at 45, and NHS internal refurbishments, at 23.
  • Over the past 12 weeks, 16 gateway 3 applications have been determined, with an approval rate of 88% and a median determination time of 20 weeks. The quickest determination was 7 weeks. This is an important area for BSR, particularly for new build projects, and BSR expects determination times to reduce as new processes are introduced and more resource is found.