Building safety regulator building control approval application data July to September 2026

Updated 9 October 2026

Applies to England

All data is correct as of 5 October 2026 and provided by the Building Safety Regulator (BSR).

Introduction

As in previous months, this Building Safety Regulator (BSR) dataset includes information relating to gateway 2 performance, with the London area performance separate.

Leading up to the building safety levy coming into effect on 1 October 2026, BSR received a significant increase in higher-risk building (HRB) applications. September submissions rose to 64 compared to 34 in August, 17 in July and 12 in June.

Our messaging in August and September highlighted that, in accordance with our normal practice, we would move to reject clearly sub-standard applications which showed significant gaps in compliance. While that remains our position, we are acutely aware of the effect that a rejection may have on the viability of a project and delivering safe new homes.

We have introduced extra checks for all applications. Any decision to invalidate or reject an application will now be reviewed through our second and third lines of assurance. We will only reject applications where there is no realistic prospect of approval within a reasonable timeframe.

While we have increased resources to manage the rise in applications, the volume of new applications means we must also apply a triage and demand management process to minimise delays on applications already in progress. We will engage with applicants on an individual basis to discuss timelines for their projects.

Gateway 2: headline numbers for July to September 2026

Status New higher-risk buildings (HRBs) and conversions External remediation
Cases in progress 186 313
Invalid or withdrawn 5 17
Decisions made 57 110
New in 114 93
Approval rate 97% 87%
Median approval time 23 weeks 32 weeks
Units approved 11,822 8,649

Commentary

  • Median approval time for new build applications shows a slight increase to 23 weeks as we have successfully closed several older cases in the last month.
  • The approval rate for new build applications has risen to 97%.
  • 57 new build decisions have been made in the last 12 weeks, up 7 from last month.
  • We have seen a notable increase in new build applications in September. There were 64 in total compared to 34 in August and 17 in July. We are attributing this to applicants submitting applications ahead of the building safety levy coming into effect on 1 October 2026. We have activated our contingency plans to deal with this expected surge.
  • External remediation median approval times have dropped from 33 to 32 weeks, with approval rates also dropping slightly from 89% to 87%. This is due to 4 recent rejections of poor applications in September. We continue to reduce the overall number of applications awaiting a decision.
  • In November 2025, approval rates were 32%, with a decision time of 44 weeks. Newer applications are progressing much faster, with those submitted in 2026 progressing positively in approximately 22 weeks.

Headline numbers for July to September 2026 – internal works and NHS

Status HRB internal works NHS internal works
Cases in progress 1,109 32
Invalid or withdrawn 133 10
Decisions made 185 26
New in 466 31
Approval rate 85% 81%
Median approval time 31 weeks 20 weeks

Commentary

  • NHS applications continue as a separate category. They have previously been reported on within the HRB internal works dataset.
  • These can include a range of building work in hospitals, from maintenance through to new hospital facilities.
  • We have been working closely with the NHS to facilitate the specialist nature of their applications.
  • The median approval time for NHS applications has dropped from 22 to 20 weeks with an associated approval rate now at 81%.
  • Internal works (category A and B) have seen approval rates increase from 78% to 85%, with approval time steady at 31 weeks.

All application categories

Week commencing New in Closed decisions Total cases in progress
13 July 46 60 1,542
20 July 47 39 1,550
27 July 56 53 1,553
3 August 62 34 1,581
10 August 48 25 1,604
17 August 71 50 1,625
24 August 100 60 1,665
31 August 41 34 1,672
7 September 50 46 1,676
14 September 46 38 1,684
21 September 77 68 1,693
28 September 74 61 1,706

Commentary

  • There are currently 1,706 gateway 2 applications in progress. This is an increase of 34 in September and reflects a rise in new build applications submitted in the lead up to the building safety levy coming into effect.
  • These include the new build, external remediation, internal refurbishment and NHS applications.
  • Transitional cases are also included. These are projects that revert to BSR when the building control body that was originally overseeing the project stops trading.
  • Commenced under the previous building control regime, they are generally much more complicated to progress. This is because much of the evidence that we now expect at gateway 2 is not available.
  • There are currently 66 transitional cases in progress at gateway 2.

New HRBs and conversions (national)

New HRBs and conversions: new in versus closed decisions (national)

Week commencing New in Closed decisions Total cases in progress
13 July 7 9 132
20 July 4 4 132
27 July 4 10 126
3 August 9 2 133
10 August 6 4 135
17 August 12 3 144
24 August 7 4 147
31 August 5 2 150
7 September 8 3 155
14 September 7 5 157
21 September 20 8 169
28 September 25 8 186

New HRBs and conversions: performance (national)

Description Total
New in 114
In progress 186
Units approved 11,822
Units in progress 40,644

New HRBs and conversions: percentages and weeks taken (national)

In the period, there were:

  • 57 decisions made
  • 5 invalid or withdrawn applications
  • 30 complex cases in progress with a median approval time of 34 weeks
Description Percentage Weeks taken (median)
Rejection rate 4% 16
Approval rate 96% 23

Commentary

  • Out of 114 applications received over the past 12 weeks, 4 applications were invalidated and 1 was withdrawn. Of the 57 decisions made, 55 were approvals and 2 were rejections.
  • This means that the 12-week rolling approval rate (not including invalidations and withdrawals) has risen to 96%, with the median approval time at 23 weeks.
  • Complex cases are now tracked separately. While the final decision is included in the rejection or approval totals, their median approval time is now at 34 weeks.
  • We have seen a significant increase in applications over the past 2 months ahead of the building safety levy coming into effect on 1 October 2026.
  • We have put contingency plans in place and allocated resources to assess applications quickly and progress good quality applications as efficiently as possible.

External remediation (national)

External remediation: new in versus closed decisions (national)

Week commencing New in Closed decisions Total cases in progress
13 July 5 16 336
20 July 10 7 339
27 July 10 11 338
3 August 8 9 337
10 August 14 5 346
17 August 6 13 339
24 August 11 16 334
31 August 2 5 331
7 September 6 13 324
14 September 9 10 323
21 September 10 15 318
28 September 2 7 313

External remediation: performance (national)

Description Total
New in 93
In progress 313
Units approved 8,649
Units in progress 26,259

External remediation: percentages and weeks taken (national)

In the period, there were:

  • 110 decisions made
  • 17 invalid or withdrawn applications
Description Percentage Weeks taken (median)
Rejection rate 13% 46
Approval rate 87% 32

Commentary

  • The rolling 12-week approval rate is 87%, with the median approval time dropping from 33 to 32 weeks. In November 2025, approval rates stood at 32% with a decision time of 44 weeks.
  • Decision times remain above target as we continue to close older cases which have been in the system for some time.
  • Only 7 legacy applications from 2024 remain. This is down from 42 at the start of 2026.
  • Applications submitted in 2026 are progressing in approximately 22 weeks with high approval rates.
  • We continue to work with the sector to help applicants improve the quality of their applications. The Remediation Toolkit is helping applicants submit stronger applications.

HRB internal works (national)

HRB internal works: new in versus closed decisions (national)

Week commencing New in Closed decisions Total cases in progress
13 July 28 26 963
20 July 29 21 971
27 July 40 28 983
3 August 41 20 1,004
10 August 25 13 1,016
17 August 51 25 1,042
24 August 78 37 1,083
31 August 27 24 1,086
7 September 32 25 1,093
14 September 29 21 1,101
21 September 45 36 1,110
28 September 41 42 1,109

HRB internal works: performance (national)

Description Total
New in 466
In progress 1,109

Percentages and weeks taken (national)

In the period, there were:

  • 185 decisions made
  • 133 invalid or withdrawn applications
Description Percentage Weeks taken (median)
Rejection rate 15% 23
Approval rate 85% 31

Commentary

  • The approval rate for internal refurbishment works in category A and B has increased to 85%, with the median determination time for approvals steady at 31 weeks.
  • New applications have been received at an average rate of 38 per week over the past 12 weeks.
  • The overall combined total is at an expected 1,109, having increased steadily over the past 12 weeks.
  • HRB internal work determinations over the past 12 weeks account for around 49% of all gateway 2 decisions. These applications include all internal refurbishment works except NHS applications.
  • Work is underway to increase capacity for dealing with internal works, which is expected to come online in the coming months.

NHS internal works (national)

NHS internal works: new in versus closed decisions (national)

Week commencing New in Closed decisions Total cases in progress
13 July 5 4 38
20 July 2 5 35
27 July 2 1 36
3 August 3 3 36
10 August 2 2 36
17 August 2 6 32
24 August 3 1 34
31 August 5 2 37
7 September 2 3 36
14 September 1 1 36
21 September 1 7 30
28 September 3 1 32

NHS internal works: performance (national)

Description Total
New in 31
In progress 32

NHS internal works: percentages and weeks taken (national)

In the period, there were:

  • 26 decisions made
  • 10 invalid or withdrawn applications
Description Percentage Weeks taken (median)
Rejection rate 19% 11
Approval rate 81% 20

Commentary

  • NHS internal works are now split from HRB internal works.
  • The approval rate for NHS internal refurbishment is currently 81%.
  • The median determination time for approvals has reduced to 20 weeks.
  • New applications have been received at an average rate of 2 to 3 per week over the past 12 weeks.
  • Overall work has increased as we received slightly more applications than were closed.

Regional distribution

Data as of 5 October 2026.

Regional gateway 2 applications (London)

Region New HRBs and conversions External remediation HRB internal works NHS internal works Transitional Total
London 111 180 749 18 0 1,058
Rest of England 50 132 335 13 30 560

Regional gateway 2 applications (rest of England)

Region New HRBs and conversions External remediation HRB internal works NHS Transitional
East 4 17 44 0 1
East Midlands 0 11 26 2 2
North East 0 10 35 2 2
North West 19 35 40 2 13
South East 8 23 47 2 4
South West 6 22 80 2 4
West Midlands 10 3 32 1 1
Yorkshire and the Humber 3 11 31 2 3

New HRBs and conversions (London)

New HRBs and conversions: new in versus closed decisions (London)

Week commencing New in Closed decisions Total cases in progress
13 July 3 3 85
20 July 2 3 84
27 July 2 7 79
3 August 6 1 84
10 August 6 1 89
17 August 10 3 96
24 August 2 2 96
31 August 3 1 98
7 September 4 2 100
14 September 4 4 100
21 September 12 8 104
28 September 11 4 111

New HRBs and conversions: performance (London)

Description Total
New in 65
In progress 111
Units approved 6,855
Units in progress 22,204

New HRBs and conversions: percentages and weeks taken (London)

In the period, there were:

  • 37 decisions made
  • 2 invalid or withdrawn applications
Description Percentage Weeks taken (median)
Approval rate 97% 22
Rejection rate 3% 23

Commentary

  • Around 60% of in progress new build applications are in London.
  • This also represents around 55% of the overall new build residential units handled by BSR.
  • 37 of the 57 new build decisions made in the last 12 weeks are in London.
  • London approval rates are 97%. This figure shows significant work to resolve outstanding complex cases.
  • Approval time for non-complex cases is 22 weeks, slightly below the national average.

External remediation (London)

External remediation: new in versus closed decisions (London)

Week commencing New in Closed decisions Total cases in progress
13 July 4 7 192
20 July 5 6 191
27 July 2 6 187
3 August 2 4 185
10 August 6 3 188
17 August 3 4 187
24 August 9 8 188
31 August 1 0 189
7 September 2 8 183
14 September 5 3 185
21 September 5 8 182
28 September 2 4 180

External remediation: performance (London)

Description Total
New in 46
In progress 180
Units approved 4,643
Units in progress 14,298

External remediation: percentages and weeks taken (London)

In the period, there were:

  • 54 decisions made
  • 7 invalid or withdrawn applications
Description Percentage Weeks taken (median)
Approval rate 96% 38
Rejection rate 4% 22

Commentary

  • Open remediation cases in London have dropped over the period from 195 to 180.
  • Progress has been made since the announcement of the BSR remediation improvement plan in April 2026. There are now 6 legacy applications from 2024 remaining, down from 42 at the start of 2026.
  • The median approval time in weeks based on the rolling total shows our effort to close older 2024 to 2025 applications, but these continue to affect the overall median approval times.
  • Applications submitted in 2026 are being determined much more quickly.
  • London approval rates of 96% are slightly higher than they are nationally.

HRB internal works (London)

HRB internal works: new in versus closed decisions (London)

Week commencing New in Closed decisions Total cases in progress
13 July 18 19 640
20 July 21 13 648
27 July 33 22 659
3 August 25 16 668
10 August 23 9 682
17 August 31 17 696
24 August 65 17 744
31 August 18 20 742
7 September 16 20 738
14 September 21 17 742
21 September 30 23 749
28 September 35 35 749

HRB internal works: performance (London)

Description Total
New in 336
In progress 749

HRB internal works: percentages and weeks taken (London)

In the period, there were:

  • 140 decisions made
  • 88 invalid or withdrawn applications
Description Percentage Weeks taken (median)
Approval rate 88% 33
Rejection rate 12% 23

Commentary

  • The approval rate for internal refurbishment works in category A and B is currently 88%, with a median determination time for approvals of 33 weeks. This is very similar to the national average.
  • The overall combined total is less than the expected total of 850 to 900. It has been steady at around 740 to 750 over the past month.
  • HRB internal work determinations over the past 12 weeks account for around 56% of gateway 2 decisions. These applications include all internal refurbishment works, except NHS applications.

NHS internal works (London)

NHS internal works: new in versus closed decisions (London)

Week commencing New in Closed decisions Total cases in progress
13 July 1 2 17
20 July 0 2 15
27 July 0 0 15
3 August 0 0 15
10 August 2 0 17
17 August 0 4 13
24 August 1 0 14
31 August 3 0 17
7 September 0 2 15
14 September 1 0 16
21 September 1 1 16
28 September 2 0 18

NHS internal works: performance (London)

Description Total
New in 11
In progress 18

NHS internal works: percentages and weeks taken (London)

In the period, there were:

  • 9 decisions made
  • 2 invalid or withdrawn applications
Description Percentage Weeks taken (median)
Approval rate 78% 20
Rejection rate 22% 14

Commentary

  • NHS internal works have now been split from HRB internal works.
  • The approval rate for NHS internal works is currently 78%, with a median determination time for approvals of 20 weeks. This is slightly higher than the national average.

Building control resources: people working on building control applications

Week commencing Internal resources External resources Total resources
13 July 149 262 411
20 July 145 264 409
27 July 142 241 383
3 August 138 236 374
10 August 142 245 387
17 August 141 239 380
24 August 141 247 388
31 August 134 250 384
7 September 146 268 414
14 September 149 274 423
21 September 154 265 419
28 September 142 235 377

Building control resources: performance

Description Total
Internal resources 181
External resources 491
Integrated resources 62

Building control resources: resource breakdown

Internal resources

Description Total
Regulatory leads 103
Principal regulatory leads 18
Case officers 56
Case officer managers 3
Administrative officers 1

External resources

Description Total
Registered building inspectors (RBIs) 239
Fire service professionals 102
Structural engineers 116
Specialists 34

Integrated resources

Description Total
Registered building inspectors (RBIs) 34
Fire service professionals 6
Structural engineers 22

Commentary

  • Sufficient internal, external and integrated resources are essential for BSR to meet demand.
  • We have grown our internal regulatory team by 25 over the past 4 months, and we are continuing to actively recruit over the next 6 to 12 months.
  • We are also growing our integrated resource teams to meet demand, see the ‘Building control integrated resources’ section.

Building control integrated resources

BSR has several specialist resources working as part of an integrated workforce within the new build and external remediation teams. We are growing this capacity to meet demand and reduce processing times.

Resource FTE as of 29 September Headcount as of 29 September October forecast (FTE) November forecast (FTE) December forecast (FTE)
Registered building inspectors 22.4 34 25.4 28 34
Structural engineers 20 22 22 24 25.6
Fire service professionals and engineers 5.6 6 5.6 5.6 10.6

Full-time equivalent (FTE) is an aggregated total of staff availability, as some people are available fewer than 5 days per week.

In build: major changes from July to September 2026

Data as of 5 October 2026.

In build: new in versus closed applications

Week commencing New in Closed applications Total cases in progress
13 July 20 7 196
20 July 9 11 194
27 July 14 19 189
3 August 9 9 189
10 August 17 9 197
17 August 18 22 193
24 August 9 7 195
31 August 11 15 191
7 September 18 11 198
14 September 11 11 198
21 September 16 3 211
28 September 14 17 208
Application type Live major change requests New in Closed Median weeks to close
New HRBs and conversions 85 92 72 7
External remediations 25 21 32 19
NHS applications 24 11 5 20
HRB internal works 71 42 33 25

Commentary

  • BSR recognises that the timely processing of major change requests during build is vital to ensure construction can continue.
  • There are currently 208 live major change requests. 142 requests have been closed in the period, including 142 shown in the data tables and zero transitional requests.
  • The median closure time for new build projects is currently at 7 weeks, just one week more than the statutory target.
  • Transitional major change requests make up the remaining 3 of the 208 not shown on the data tables, with zero new in and zero closed.

Gateway 3 applications

Data as of 5 October 2026.

Gateway 3 applications: new in versus closed applications

Week commencing New in Closed applications Total cases in progress
13 July 3 3 131
20 July 3 2 132
27 July 4 1 135
3 August 7 0 142
10 August 4 0 146
17 August 9 1 154
24 August 9 1 162
31 August 5 0 167
7 September 4 2 169
14 September 1 2 168
21 September 6 0 174
28 September 1 0 175

Gateway 3 applications: performance

Application type In progress Units Approvals New in
New HRBs and conversions 0 0 0 0
External remediation 8 972 0 3
NHS internal works 19 0 3 3
HRB internal works 122 0 2 48

Commentary

  • No new build projects that have passed through gateway 2 have reached gateway 3.
  • Inspection regime for new build projects has highlighted a small amount of building work that deviates from designs agreed in gateway 2.
  • Of the 361 gateway 3 applications received, 274 are internal refurbishments. Most of the remainder are transitional cases (42) and NHS internal refurbishments (27).
  • Over the past 12 weeks, 9 gateway 3 applications have been determined with an approval rate of 100% and a median determination time of 20 weeks. The quickest determination was 16 weeks. This is an important area for BSR, particularly for new build projects, and we expect determination times to reduce as new processes are introduced and more resource is found.