All data is correct as of 5 October 2026 and provided by the Building Safety Regulator (BSR).
Introduction
As in previous months, this Building Safety Regulator (BSR) dataset includes information relating to gateway 2 performance, with the London area performance separate.
Recent trends
Leading up to the building safety levy coming into effect on 1 October 2026, BSR received a significant increase in higher-risk building (HRB) applications. September submissions rose to 64 compared to 34 in August, 17 in July and 12 in June.
Our messaging in August and September highlighted that, in accordance with our normal practice, we would move to reject clearly sub-standard applications which showed significant gaps in compliance. While that remains our position, we are acutely aware of the effect that a rejection may have on the viability of a project and delivering safe new homes.
We have introduced extra checks for all applications. Any decision to invalidate or reject an application will now be reviewed through our second and third lines of assurance. We will only reject applications where there is no realistic prospect of approval within a reasonable timeframe.
While we have increased resources to manage the rise in applications, the volume of new applications means we must also apply a triage and demand management process to minimise delays on applications already in progress. We will engage with applicants on an individual basis to discuss timelines for their projects.
Gateway 2: headline numbers for July to September 2026
| Status |
New higher-risk buildings (HRBs) and conversions |
External remediation |
| Cases in progress |
186 |
313 |
| Invalid or withdrawn |
5 |
17 |
| Decisions made |
57 |
110 |
| New in |
114 |
93 |
| Approval rate |
97% |
87% |
| Median approval time |
23 weeks |
32 weeks |
| Units approved |
11,822 |
8,649 |
- Median approval time for new build applications shows a slight increase to 23 weeks as we have successfully closed several older cases in the last month.
- The approval rate for new build applications has risen to 97%.
- 57 new build decisions have been made in the last 12 weeks, up 7 from last month.
- We have seen a notable increase in new build applications in September. There were 64 in total compared to 34 in August and 17 in July. We are attributing this to applicants submitting applications ahead of the building safety levy coming into effect on 1 October 2026. We have activated our contingency plans to deal with this expected surge.
- External remediation median approval times have dropped from 33 to 32 weeks, with approval rates also dropping slightly from 89% to 87%. This is due to 4 recent rejections of poor applications in September. We continue to reduce the overall number of applications awaiting a decision.
- In November 2025, approval rates were 32%, with a decision time of 44 weeks. Newer applications are progressing much faster, with those submitted in 2026 progressing positively in approximately 22 weeks.
Headline numbers for July to September 2026 – internal works and NHS
| Status |
HRB internal works |
NHS internal works |
| Cases in progress |
1,109 |
32 |
| Invalid or withdrawn |
133 |
10 |
| Decisions made |
185 |
26 |
| New in |
466 |
31 |
| Approval rate |
85% |
81% |
| Median approval time |
31 weeks |
20 weeks |
-
NHS applications continue as a separate category. They have previously been reported on within the HRB internal works dataset.
- These can include a range of building work in hospitals, from maintenance through to new hospital facilities.
- We have been working closely with the NHS to facilitate the specialist nature of their applications.
- The median approval time for NHS applications has dropped from 22 to 20 weeks with an associated approval rate now at 81%.
- Internal works (category A and B) have seen approval rates increase from 78% to 85%, with approval time steady at 31 weeks.
All application categories
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 13 July |
46 |
60 |
1,542 |
| 20 July |
47 |
39 |
1,550 |
| 27 July |
56 |
53 |
1,553 |
| 3 August |
62 |
34 |
1,581 |
| 10 August |
48 |
25 |
1,604 |
| 17 August |
71 |
50 |
1,625 |
| 24 August |
100 |
60 |
1,665 |
| 31 August |
41 |
34 |
1,672 |
| 7 September |
50 |
46 |
1,676 |
| 14 September |
46 |
38 |
1,684 |
| 21 September |
77 |
68 |
1,693 |
| 28 September |
74 |
61 |
1,706 |
- There are currently 1,706 gateway 2 applications in progress. This is an increase of 34 in September and reflects a rise in new build applications submitted in the lead up to the building safety levy coming into effect.
- These include the new build, external remediation, internal refurbishment and NHS applications.
- Transitional cases are also included. These are projects that revert to BSR when the building control body that was originally overseeing the project stops trading.
- Commenced under the previous building control regime, they are generally much more complicated to progress. This is because much of the evidence that we now expect at gateway 2 is not available.
- There are currently 66 transitional cases in progress at gateway 2.
New HRBs and conversions (national)
New HRBs and conversions: new in versus closed decisions (national)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 13 July |
7 |
9 |
132 |
| 20 July |
4 |
4 |
132 |
| 27 July |
4 |
10 |
126 |
| 3 August |
9 |
2 |
133 |
| 10 August |
6 |
4 |
135 |
| 17 August |
12 |
3 |
144 |
| 24 August |
7 |
4 |
147 |
| 31 August |
5 |
2 |
150 |
| 7 September |
8 |
3 |
155 |
| 14 September |
7 |
5 |
157 |
| 21 September |
20 |
8 |
169 |
| 28 September |
25 |
8 |
186 |
| Description |
Total |
| New in |
114 |
| In progress |
186 |
| Units approved |
11,822 |
| Units in progress |
40,644 |
New HRBs and conversions: percentages and weeks taken (national)
In the period, there were:
- 57 decisions made
- 5 invalid or withdrawn applications
- 30 complex cases in progress with a median approval time of 34 weeks
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
4% |
16 |
| Approval rate |
96% |
23 |
- Out of 114 applications received over the past 12 weeks, 4 applications were invalidated and 1 was withdrawn. Of the 57 decisions made, 55 were approvals and 2 were rejections.
- This means that the 12-week rolling approval rate (not including invalidations and withdrawals) has risen to 96%, with the median approval time at 23 weeks.
- Complex cases are now tracked separately. While the final decision is included in the rejection or approval totals, their median approval time is now at 34 weeks.
- We have seen a significant increase in applications over the past 2 months ahead of the building safety levy coming into effect on 1 October 2026.
- We have put contingency plans in place and allocated resources to assess applications quickly and progress good quality applications as efficiently as possible.
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 13 July |
5 |
16 |
336 |
| 20 July |
10 |
7 |
339 |
| 27 July |
10 |
11 |
338 |
| 3 August |
8 |
9 |
337 |
| 10 August |
14 |
5 |
346 |
| 17 August |
6 |
13 |
339 |
| 24 August |
11 |
16 |
334 |
| 31 August |
2 |
5 |
331 |
| 7 September |
6 |
13 |
324 |
| 14 September |
9 |
10 |
323 |
| 21 September |
10 |
15 |
318 |
| 28 September |
2 |
7 |
313 |
| Description |
Total |
| New in |
93 |
| In progress |
313 |
| Units approved |
8,649 |
| Units in progress |
26,259 |
In the period, there were:
- 110 decisions made
- 17 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
13% |
46 |
| Approval rate |
87% |
32 |
- The rolling 12-week approval rate is 87%, with the median approval time dropping from 33 to 32 weeks. In November 2025, approval rates stood at 32% with a decision time of 44 weeks.
- Decision times remain above target as we continue to close older cases which have been in the system for some time.
- Only 7 legacy applications from 2024 remain. This is down from 42 at the start of 2026.
- Applications submitted in 2026 are progressing in approximately 22 weeks with high approval rates.
- We continue to work with the sector to help applicants improve the quality of their applications. The Remediation Toolkit is helping applicants submit stronger applications.
HRB internal works (national)
HRB internal works: new in versus closed decisions (national)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 13 July |
28 |
26 |
963 |
| 20 July |
29 |
21 |
971 |
| 27 July |
40 |
28 |
983 |
| 3 August |
41 |
20 |
1,004 |
| 10 August |
25 |
13 |
1,016 |
| 17 August |
51 |
25 |
1,042 |
| 24 August |
78 |
37 |
1,083 |
| 31 August |
27 |
24 |
1,086 |
| 7 September |
32 |
25 |
1,093 |
| 14 September |
29 |
21 |
1,101 |
| 21 September |
45 |
36 |
1,110 |
| 28 September |
41 |
42 |
1,109 |
| Description |
Total |
| New in |
466 |
| In progress |
1,109 |
Percentages and weeks taken (national)
In the period, there were:
- 185 decisions made
- 133 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
15% |
23 |
| Approval rate |
85% |
31 |
- The approval rate for internal refurbishment works in category A and B has increased to 85%, with the median determination time for approvals steady at 31 weeks.
- New applications have been received at an average rate of 38 per week over the past 12 weeks.
- The overall combined total is at an expected 1,109, having increased steadily over the past 12 weeks.
-
HRB internal work determinations over the past 12 weeks account for around 49% of all gateway 2 decisions. These applications include all internal refurbishment works except NHS applications.
- Work is underway to increase capacity for dealing with internal works, which is expected to come online in the coming months.
NHS internal works (national)
NHS internal works: new in versus closed decisions (national)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 13 July |
5 |
4 |
38 |
| 20 July |
2 |
5 |
35 |
| 27 July |
2 |
1 |
36 |
| 3 August |
3 |
3 |
36 |
| 10 August |
2 |
2 |
36 |
| 17 August |
2 |
6 |
32 |
| 24 August |
3 |
1 |
34 |
| 31 August |
5 |
2 |
37 |
| 7 September |
2 |
3 |
36 |
| 14 September |
1 |
1 |
36 |
| 21 September |
1 |
7 |
30 |
| 28 September |
3 |
1 |
32 |
| Description |
Total |
| New in |
31 |
| In progress |
32 |
NHS internal works: percentages and weeks taken (national)
In the period, there were:
- 26 decisions made
- 10 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejection rate |
19% |
11 |
| Approval rate |
81% |
20 |
-
NHS internal works are now split from HRB internal works.
- The approval rate for NHS internal refurbishment is currently 81%.
- The median determination time for approvals has reduced to 20 weeks.
- New applications have been received at an average rate of 2 to 3 per week over the past 12 weeks.
- Overall work has increased as we received slightly more applications than were closed.
Regional distribution
Data as of 5 October 2026.
Regional gateway 2 applications (London)
| Region |
New HRBs and conversions |
External remediation |
HRB internal works |
NHS internal works |
Transitional |
Total |
| London |
111 |
180 |
749 |
18 |
0 |
1,058 |
| Rest of England |
50 |
132 |
335 |
13 |
30 |
560 |
Regional gateway 2 applications (rest of England)
| Region |
New HRBs and conversions |
External remediation |
HRB internal works |
NHS |
Transitional |
| East |
4 |
17 |
44 |
0 |
1 |
| East Midlands |
0 |
11 |
26 |
2 |
2 |
| North East |
0 |
10 |
35 |
2 |
2 |
| North West |
19 |
35 |
40 |
2 |
13 |
| South East |
8 |
23 |
47 |
2 |
4 |
| South West |
6 |
22 |
80 |
2 |
4 |
| West Midlands |
10 |
3 |
32 |
1 |
1 |
| Yorkshire and the Humber |
3 |
11 |
31 |
2 |
3 |
New HRBs and conversions (London)
New HRBs and conversions: new in versus closed decisions (London)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 13 July |
3 |
3 |
85 |
| 20 July |
2 |
3 |
84 |
| 27 July |
2 |
7 |
79 |
| 3 August |
6 |
1 |
84 |
| 10 August |
6 |
1 |
89 |
| 17 August |
10 |
3 |
96 |
| 24 August |
2 |
2 |
96 |
| 31 August |
3 |
1 |
98 |
| 7 September |
4 |
2 |
100 |
| 14 September |
4 |
4 |
100 |
| 21 September |
12 |
8 |
104 |
| 28 September |
11 |
4 |
111 |
| Description |
Total |
| New in |
65 |
| In progress |
111 |
| Units approved |
6,855 |
| Units in progress |
22,204 |
New HRBs and conversions: percentages and weeks taken (London)
In the period, there were:
- 37 decisions made
- 2 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Approval rate |
97% |
22 |
| Rejection rate |
3% |
23 |
- Around 60% of in progress new build applications are in London.
- This also represents around 55% of the overall new build residential units handled by BSR.
- 37 of the 57 new build decisions made in the last 12 weeks are in London.
- London approval rates are 97%. This figure shows significant work to resolve outstanding complex cases.
- Approval time for non-complex cases is 22 weeks, slightly below the national average.
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 13 July |
4 |
7 |
192 |
| 20 July |
5 |
6 |
191 |
| 27 July |
2 |
6 |
187 |
| 3 August |
2 |
4 |
185 |
| 10 August |
6 |
3 |
188 |
| 17 August |
3 |
4 |
187 |
| 24 August |
9 |
8 |
188 |
| 31 August |
1 |
0 |
189 |
| 7 September |
2 |
8 |
183 |
| 14 September |
5 |
3 |
185 |
| 21 September |
5 |
8 |
182 |
| 28 September |
2 |
4 |
180 |
| Description |
Total |
| New in |
46 |
| In progress |
180 |
| Units approved |
4,643 |
| Units in progress |
14,298 |
In the period, there were:
- 54 decisions made
- 7 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Approval rate |
96% |
38 |
| Rejection rate |
4% |
22 |
- Open remediation cases in London have dropped over the period from 195 to 180.
- Progress has been made since the announcement of the BSR remediation improvement plan in April 2026. There are now 6 legacy applications from 2024 remaining, down from 42 at the start of 2026.
- The median approval time in weeks based on the rolling total shows our effort to close older 2024 to 2025 applications, but these continue to affect the overall median approval times.
- Applications submitted in 2026 are being determined much more quickly.
- London approval rates of 96% are slightly higher than they are nationally.
HRB internal works (London)
HRB internal works: new in versus closed decisions (London)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 13 July |
18 |
19 |
640 |
| 20 July |
21 |
13 |
648 |
| 27 July |
33 |
22 |
659 |
| 3 August |
25 |
16 |
668 |
| 10 August |
23 |
9 |
682 |
| 17 August |
31 |
17 |
696 |
| 24 August |
65 |
17 |
744 |
| 31 August |
18 |
20 |
742 |
| 7 September |
16 |
20 |
738 |
| 14 September |
21 |
17 |
742 |
| 21 September |
30 |
23 |
749 |
| 28 September |
35 |
35 |
749 |
| Description |
Total |
| New in |
336 |
| In progress |
749 |
HRB internal works: percentages and weeks taken (London)
In the period, there were:
- 140 decisions made
- 88 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Approval rate |
88% |
33 |
| Rejection rate |
12% |
23 |
- The approval rate for internal refurbishment works in category A and B is currently 88%, with a median determination time for approvals of 33 weeks. This is very similar to the national average.
- The overall combined total is less than the expected total of 850 to 900. It has been steady at around 740 to 750 over the past month.
-
HRB internal work determinations over the past 12 weeks account for around 56% of gateway 2 decisions. These applications include all internal refurbishment works, except NHS applications.
NHS internal works (London)
NHS internal works: new in versus closed decisions (London)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 13 July |
1 |
2 |
17 |
| 20 July |
0 |
2 |
15 |
| 27 July |
0 |
0 |
15 |
| 3 August |
0 |
0 |
15 |
| 10 August |
2 |
0 |
17 |
| 17 August |
0 |
4 |
13 |
| 24 August |
1 |
0 |
14 |
| 31 August |
3 |
0 |
17 |
| 7 September |
0 |
2 |
15 |
| 14 September |
1 |
0 |
16 |
| 21 September |
1 |
1 |
16 |
| 28 September |
2 |
0 |
18 |
| Description |
Total |
| New in |
11 |
| In progress |
18 |
NHS internal works: percentages and weeks taken (London)
In the period, there were:
- 9 decisions made
- 2 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Approval rate |
78% |
20 |
| Rejection rate |
22% |
14 |
-
NHS internal works have now been split from HRB internal works.
- The approval rate for NHS internal works is currently 78%, with a median determination time for approvals of 20 weeks. This is slightly higher than the national average.
Building control resources: people working on building control applications
| Week commencing |
Internal resources |
External resources |
Total resources |
| 13 July |
149 |
262 |
411 |
| 20 July |
145 |
264 |
409 |
| 27 July |
142 |
241 |
383 |
| 3 August |
138 |
236 |
374 |
| 10 August |
142 |
245 |
387 |
| 17 August |
141 |
239 |
380 |
| 24 August |
141 |
247 |
388 |
| 31 August |
134 |
250 |
384 |
| 7 September |
146 |
268 |
414 |
| 14 September |
149 |
274 |
423 |
| 21 September |
154 |
265 |
419 |
| 28 September |
142 |
235 |
377 |
| Description |
Total |
| Internal resources |
181 |
| External resources |
491 |
| Integrated resources |
62 |
Building control resources: resource breakdown
Internal resources
| Description |
Total |
| Regulatory leads |
103 |
| Principal regulatory leads |
18 |
| Case officers |
56 |
| Case officer managers |
3 |
| Administrative officers |
1 |
External resources
| Description |
Total |
| Registered building inspectors (RBIs) |
239 |
| Fire service professionals |
102 |
| Structural engineers |
116 |
| Specialists |
34 |
Integrated resources
| Description |
Total |
| Registered building inspectors (RBIs) |
34 |
| Fire service professionals |
6 |
| Structural engineers |
22 |
- Sufficient internal, external and integrated resources are essential for BSR to meet demand.
- We have grown our internal regulatory team by 25 over the past 4 months, and we are continuing to actively recruit over the next 6 to 12 months.
- We are also growing our integrated resource teams to meet demand, see the ‘Building control integrated resources’ section.
Building control integrated resources
BSR has several specialist resources working as part of an integrated workforce within the new build and external remediation teams. We are growing this capacity to meet demand and reduce processing times.
| Resource |
FTE as of 29 September |
Headcount as of 29 September |
October forecast (FTE) |
November forecast (FTE) |
December forecast (FTE) |
| Registered building inspectors |
22.4 |
34 |
25.4 |
28 |
34 |
| Structural engineers |
20 |
22 |
22 |
24 |
25.6 |
| Fire service professionals and engineers |
5.6 |
6 |
5.6 |
5.6 |
10.6 |
Full-time equivalent (FTE) is an aggregated total of staff availability, as some people are available fewer than 5 days per week.
In build: major changes from July to September 2026
Data as of 5 October 2026.
In build: new in versus closed applications
| Week commencing |
New in |
Closed applications |
Total cases in progress |
| 13 July |
20 |
7 |
196 |
| 20 July |
9 |
11 |
194 |
| 27 July |
14 |
19 |
189 |
| 3 August |
9 |
9 |
189 |
| 10 August |
17 |
9 |
197 |
| 17 August |
18 |
22 |
193 |
| 24 August |
9 |
7 |
195 |
| 31 August |
11 |
15 |
191 |
| 7 September |
18 |
11 |
198 |
| 14 September |
11 |
11 |
198 |
| 21 September |
16 |
3 |
211 |
| 28 September |
14 |
17 |
208 |
| Application type |
Live major change requests |
New in |
Closed |
Median weeks to close |
| New HRBs and conversions |
85 |
92 |
72 |
7 |
| External remediations |
25 |
21 |
32 |
19 |
|
NHS applications |
24 |
11 |
5 |
20 |
|
HRB internal works |
71 |
42 |
33 |
25 |
-
BSR recognises that the timely processing of major change requests during build is vital to ensure construction can continue.
- There are currently 208 live major change requests. 142 requests have been closed in the period, including 142 shown in the data tables and zero transitional requests.
- The median closure time for new build projects is currently at 7 weeks, just one week more than the statutory target.
- Transitional major change requests make up the remaining 3 of the 208 not shown on the data tables, with zero new in and zero closed.
Gateway 3 applications
Data as of 5 October 2026.
Gateway 3 applications: new in versus closed applications
| Week commencing |
New in |
Closed applications |
Total cases in progress |
| 13 July |
3 |
3 |
131 |
| 20 July |
3 |
2 |
132 |
| 27 July |
4 |
1 |
135 |
| 3 August |
7 |
0 |
142 |
| 10 August |
4 |
0 |
146 |
| 17 August |
9 |
1 |
154 |
| 24 August |
9 |
1 |
162 |
| 31 August |
5 |
0 |
167 |
| 7 September |
4 |
2 |
169 |
| 14 September |
1 |
2 |
168 |
| 21 September |
6 |
0 |
174 |
| 28 September |
1 |
0 |
175 |
| Application type |
In progress |
Units |
Approvals |
New in |
| New HRBs and conversions |
0 |
0 |
0 |
0 |
| External remediation |
8 |
972 |
0 |
3 |
|
NHS internal works |
19 |
0 |
3 |
3 |
|
HRB internal works |
122 |
0 |
2 |
48 |
- No new build projects that have passed through gateway 2 have reached gateway 3.
- Inspection regime for new build projects has highlighted a small amount of building work that deviates from designs agreed in gateway 2.
- Of the 361 gateway 3 applications received, 274 are internal refurbishments. Most of the remainder are transitional cases (42) and NHS internal refurbishments (27).
- Over the past 12 weeks, 9 gateway 3 applications have been determined with an approval rate of 100% and a median determination time of 20 weeks. The quickest determination was 16 weeks. This is an important area for BSR, particularly for new build projects, and we expect determination times to reduce as new processes are introduced and more resource is found.