All data is correct as of 28 June 2026 and provided by the Building Safety Regulator (BSR).
Introduction
As in previous months, this dataset includes information relating to gateway 2 performance in England. The London area performance is separate.
New information this month includes:
- a summary of gateway 2 applications across all categories, with internal refurbishment as a separate category for the first time
- new gateway 2 data for internal refurbishment and transitional applications
- a change to the London versus regional breakdown to show all categories of application
- revised data showing the overall numbers and breakdown of people working on building control applications, both within and outside of BSR
- early performance indicators for gateway 3, mostly covering internal refurbishment works with no new builds via gateway 2 currently in scope
Gateway 2: headline numbers for April to June 2026
| Status |
New higher-risk buildings (HRBs) and conversions |
External remediation |
HRB internal works (category A and B) |
| Cases in progress |
138 |
342 |
952 |
| Invalid or withdrawn |
17 |
12 |
299 |
| Decisions made |
37 |
85 |
237 |
| New in |
57 |
103 |
517 |
| Approval rate |
89% |
85% |
73% |
| Median approval time |
22 weeks |
35 weeks |
28 weeks |
| Units approved |
6,544 |
4,998 |
Not applicable |
All application categories
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 6 Apr |
47 |
40 |
1536 |
| 13 Apr |
50 |
37 |
1549 |
| 20 Apr |
62 |
62 |
1549 |
| 27 Apr |
66 |
69 |
1546 |
| 4 May |
78 |
51 |
1573 |
| 11 May |
72 |
122 |
1523 |
| 18 May |
57 |
89 |
1491 |
| 25 May |
42 |
53 |
1480 |
| 1 Jun |
80 |
59 |
1501 |
| 8 Jun |
53 |
51 |
1503 |
| 15 Jun |
50 |
49 |
1504 |
| 22 Jun |
48 |
47 |
1505 |
- There are currently 1,505 gateway 2 applications in progress. The numbers have dropped slightly over the past 12 weeks.
- These include the new build, external remediation and internal refurbishment applications.
- Transitional cases are also included. These are projects that revert to BSR when the building control body that was originally overseeing the project stops trading. These cases are not generally straightforward to progress, as much of the evidence that we now expect at gateway 2 is unavailable.
- There are currently 73 transitional cases in progress at gateway 2.
New HRBs and conversions (national)
New HRBs and conversions: new in versus closed decisions (national)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 6 Apr |
3 |
2 |
136 |
| 13 Apr |
4 |
4 |
136 |
| 20 Apr |
3 |
4 |
135 |
| 27 Apr |
9 |
5 |
139 |
| 4 May |
5 |
4 |
140 |
| 11 May |
5 |
5 |
140 |
| 18 May |
9 |
5 |
144 |
| 25 May |
3 |
10 |
137 |
| 1 Jun |
7 |
3 |
141 |
| 8 Jun |
2 |
3 |
140 |
| 15 Jun |
4 |
5 |
139 |
| 22 Jun |
3 |
4 |
138 |
| Description |
Total |
| New in |
57 |
| In progress |
138 |
| Units approved |
6,544 |
| Units in progress |
30,383 |
New HRBs and conversions: percentages and weeks taken (national)
In the period, there were:
- 37 decisions made
- 17 invalid or withdrawn applications
- 13 complex cases in progress with a median approval time of 32 weeks
| Description |
Percentage |
Weeks taken (median) |
| Rejections |
11% |
6 |
| Approval |
89% |
22 |
- Out of 57 applications received over the past 12 weeks, 11 applications were invalidated and 6 withdrawn. Of the 37 decisions made, 33 were approvals and 4 were rejections.
- The 12-week rolling approval rate (not including invalidations and withdrawals) has risen to 89%, with the median approval time at 22 weeks.
- This data shows a mix of older and newer cases, as 3 applications were approved at 15 weeks in the last month.
- Complex cases are now tracked separately. While the final decision is included in the rejection or approval totals, their median approval time is now at 32 weeks.
- We continue to work closely with industry on a shared understanding of compliance as we try to reduce the number of complex cases in the system.
- The overall combined total is 138, which is a slight decrease over the past month.
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 6 Apr |
6 |
2 |
340 |
| 13 Apr |
7 |
3 |
344 |
| 20 Apr |
17 |
3 |
358 |
| 27 Apr |
9 |
13 |
354 |
| 4 May |
8 |
5 |
357 |
| 11 May |
7 |
4 |
360 |
| 18 May |
9 |
8 |
361 |
| 25 May |
9 |
7 |
363 |
| 1 Jun |
10 |
16 |
357 |
| 8 Jun |
9 |
12 |
354 |
| 15 Jun |
6 |
15 |
345 |
| 22 Jun |
6 |
9 |
342 |
| Description |
Total |
| New in |
103 |
| In progress |
342 |
| Units approved |
4,998 |
| Units in progress |
30,962 |
In the period, there were:
- 85 decisions made
- 12 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejections |
15% |
26 |
| Approval |
85% |
35 |
- The rolling 12-week approval rate has risen to 85%, with the median approval time remaining at 35 weeks. This is due to the inclusion of older cases, as decisions continue to be made on applications that have been in the system for some time.
- 14 legacy applications made in 2024 now remain, down from 42 at the start of 2026.
- Work continues with the sector to help applicants improve the quality of applications. Data shows that applications submitted in October to December 2025 are progressing through the system faster than earlier applications. However, the approval time based on the rolling total includes 2024 to 2025 applications being cleared. This contributes to the higher figure.
- New guidance setting out the level of detail expected in applications and common shortfalls was published on 22 June 2026.
HRB internal works (national)
HRB internal works: new in versus closed decisions (national)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 6 Apr |
36 |
34 |
973 |
| 13 Apr |
37 |
30 |
980 |
| 20 Apr |
40 |
53 |
967 |
| 27 Apr |
47 |
49 |
965 |
| 4 May |
60 |
35 |
990 |
| 11 May |
58 |
105 |
943 |
| 18 May |
36 |
70 |
909 |
| 25 May |
28 |
33 |
904 |
| 1 Jun |
61 |
35 |
930 |
| 8 Jun |
36 |
32 |
934 |
| 15 Jun |
39 |
26 |
947 |
| 22 Jun |
39 |
34 |
952 |
| Description |
Total |
| New in |
517 |
| In progress |
952 |
| Decisions made |
237 |
| Invalid / withdrawn |
299 |
HRB internal works: percentages and weeks taken (national)
In the period, there were:
- 237 decisions made
- 299 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejections |
27% |
25 |
| Approval |
73% |
28 |
- The approval rate for internal refurbishment works in category A and B is currently 73%, with a median determination time for approvals of 28 weeks.
- New applications have been received at an average rate of around 43 per week over the past 12 weeks. Using the current median determination period of 28 weeks this suggests that the overall total should be around 1,200 to 1,250 applications.
- As determination times reduce, the total number of applications in progress would be expected to reduce accordingly.
- The overall combined total is currently 952 and has decreased slightly over the past 12 weeks.
-
HRB internal work determinations over the past 12 weeks account for around 64% of all gateway 2 decisions. These applications include all internal refurbishment works, as well as NHS applications.
Gateway 2: regional distribution
Data as of the 28 June 2026.
Regional gateway 2 applications (London)
| Region |
New HRBs and conversions |
External remediation |
Internal works |
Transitional |
Total |
| London |
89 |
192 |
619 |
0 |
900 |
| Rest of country |
41 |
149 |
316 |
0 |
506 |
Regional gateway 2 applications (rest of England)
| Region |
New HRBs and conversions |
External remediation |
HRB internal works |
Transitional |
Total |
| East |
0 |
21 |
37 |
0 |
58 |
| East Midlands |
0 |
10 |
24 |
0 |
34 |
| North East |
0 |
6 |
36 |
0 |
42 |
| North West |
19 |
49 |
32 |
0 |
100 |
| South East |
9 |
31 |
46 |
0 |
86 |
| South West |
4 |
16 |
69 |
0 |
89 |
| West Midlands |
5 |
5 |
29 |
0 |
39 |
| Yorkshire and The Humber |
4 |
11 |
43 |
0 |
58 |
New HRBs and conversions (London)
New HRBs and conversions: new in versus closed decisions (London)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 6 Apr |
3 |
1 |
82 |
| 13 Apr |
3 |
3 |
82 |
| 20 Apr |
2 |
1 |
83 |
| 27 Apr |
5 |
2 |
86 |
| 4 May |
4 |
3 |
87 |
| 11 May |
5 |
3 |
89 |
| 18 May |
7 |
4 |
92 |
| 25 May |
3 |
4 |
91 |
| 1 Jun |
4 |
2 |
93 |
| 8 Jun |
1 |
2 |
92 |
| 15 Jun |
1 |
4 |
89 |
| 22 Jun |
2 |
2 |
89 |
| Description |
Total |
| New in |
40 |
| In progress |
89 |
| Units approved |
3,559 |
| Units in progress |
17,010 |
New HRBs and conversions: percentages and weeks taken (London)
In the period, there were:
- 22 decisions made
- 6 invalid or withdrawn applications
- 7 complex cases in progress with a median approval time of 29 weeks
| Description |
Percentage |
Weeks taken (median) |
| Rejections |
9% |
6 |
| Approval |
91% |
22 |
- Around 59% of in-progress new build applications are in London.
- This also represents around 55% of the overall new build residential units handled by BSR.
- 20 of the 28 new build decisions made in the last 12 weeks are in London.
- London approval rates are 91%. This figure shows significant work to resolve outstanding complex cases.
- Approval time for non-complex cases is 22 weeks, the same as the national average.
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 6 Apr |
3 |
1 |
183 |
| 13 Apr |
15 |
1 |
185 |
| 20 Apr |
1 |
2 |
198 |
| 27 Apr |
6 |
8 |
191 |
| 4 May |
4 |
2 |
195 |
| 11 May |
7 |
1 |
198 |
| 18 May |
6 |
4 |
201 |
| 25 May |
6 |
3 |
204 |
| 1 Jun |
4 |
10 |
200 |
| 8 Jun |
4 |
4 |
200 |
| 15 Jun |
2 |
9 |
195 |
| 22 Jun |
0 |
5 |
192 |
| Description |
Total |
| New in |
58 |
| In progress |
192 |
| Units approved |
2,094 |
| Units in progress |
17,259 |
In the period, there were:
- 44 decisions made
- 6 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejections |
14% |
26 |
| Approval |
86% |
36 |
- Open remediation cases in London have increased from 184 to 192 over the period.
- The BSR remediation improvement plan was announced in April 2026.
-
BSR has already made progress, with 14 legacy 2024 applications now remaining, down from 42 at the start of 2026.
- The median approval time reflects our ambition to close older 2024 to 2025 applications. This is skewing the overall median approval times.
- Applications submitted in 2026 are being determined much more quickly.
- 2026 approval rates already exceed the greater than 65% target for 2026 at 86%.
- London approval rates of 86% are slightly higher than they are nationally.
HRB internal works (London)
HRB internal works: new in versus closed decisions (London)
| Week commencing |
New in |
Closed decisions |
Total cases in progress |
| 6 Apr |
22 |
27 |
631 |
| 13 Apr |
27 |
19 |
639 |
| 20 Apr |
25 |
28 |
636 |
| 27 Apr |
27 |
28 |
635 |
| 4 May |
27 |
22 |
640 |
| 11 May |
25 |
72 |
593 |
| 18 May |
23 |
38 |
578 |
| 25 May |
23 |
21 |
580 |
| 1 Jun |
36 |
24 |
592 |
| 8 Jun |
25 |
15 |
602 |
| 15 Jun |
31 |
19 |
614 |
| 22 Jun |
26 |
21 |
619 |
| Description |
Total |
| New in |
317 |
| In progress |
619 |
HRB internal works: percentages and weeks taken (London)
In the period, there were:
- 141 decisions made
- 193 invalid or withdrawn applications
| Description |
Percentage |
Weeks taken (median) |
| Rejections |
26% |
26 |
| Approval |
74% |
28 |
- The approval rate for internal refurbishment works in category A and B is currently 74%, with a median determination time for approvals of 28 weeks. This is very similar to the national average.
- The overall combined total is less than expected. It is currently sitting at 619, having decreased slightly over the past 12 weeks.
-
HRB internal work determinations over the past 12 weeks account for around 64% of gateway 2 decisions. These applications include all internal refurbishment works, as well as NHS applications.
Building control resources: people working on building control applications
| Week commencing |
Internal resources |
External resources |
Total resources |
| 6 Apr |
90 |
206 |
296 |
| 13 Apr |
93 |
239 |
332 |
| 20 Apr |
95 |
249 |
344 |
| 27 Apr |
99 |
246 |
345 |
| 4 May |
90 |
240 |
330 |
| 11 May |
94 |
247 |
341 |
| 18 May |
100 |
256 |
356 |
| 25 May |
89 |
235 |
324 |
| 1 Jun |
100 |
275 |
375 |
| 8 Jun |
108 |
269 |
377 |
| 15 Jun |
111 |
245 |
356 |
| 22 Jun |
115 |
220 |
335 |
| Description |
Total |
| Internal resources |
152 |
| External resources |
493 |
| Integrated resources |
64 |
Building control resources: resource breakdown
Internal resources
| Description |
Total |
| Regulatory leads |
91 |
| Principal regulatory leads |
15 |
| Case officers |
43 |
| Case officer managers |
3 |
External resources
| Description |
Total |
| Registered building inspectors (RBIs) |
222 |
| Fire service professionals |
108 |
| Structural engineers |
125 |
| Specialists |
38 |
Integrated resources
| Description |
Total |
| Registered building inspectors (RBIs) |
36 |
| Fire service professionals |
8 |
| Structural engineers |
20 |
- Sufficient internal, external and integrated resources are essential for BSR to meet demand.
- Internal regulatory teams have grown by 25 people over the past 3 months and recruitment activity is continuing over the next 6 to 12 months.
- 152 internal staff members have been involved in building control applications, including 91 regulatory leads, 15 principal regulatory leads, 43 case officers and 3 case officer managers.
- 493 people from external organisations have been involved in building control applications, including registered building inspectors, fire service professionals, structural engineers and specialists.
- Of the 493 external resources, 64 are integrated into BSR’s Innovation Unit or external remediation teams. This includes 36 registered building inspectors, 8 fire service professionals and 20 structural engineers.
Building control integrated resources
BSR has several specialist resources working as part of an integrated workforce within the new build and external remediation teams. We are growing this capacity to meet demand and reduce processing times.
Note that full-time equivalent (FTE) is an aggregated total of staff availability, as some people are available fewer than 5 days per week.
| Resource |
FTE as of 29 June |
Headcount as of 29 June |
July forecast (FTE) |
August forecast (FTE) |
September forecast (FTE) |
| Registered building inspectors |
23.9 |
36 |
27.2 |
31 |
36 |
| Structural engineers |
18.2 |
20 |
18.2 |
20.2 |
23.2 |
| Fire service professionals and engineers |
8 |
8 |
8 |
8 |
13 |
| Total |
50.1 |
64 |
53.4 |
59.2 |
72.2 |
Gateway 3 applications
Data as of the 28 June 2026.
Gateway 3 applications: application types
| Application type |
New in |
Approvals |
Units approved |
In progress |
| New HRBs and conversions |
0 |
0 |
0 |
0 |
| External remediation |
4 |
3 |
325 |
6 |
|
HRB internal works |
31 |
17 |
Not applicable |
98 |
| Transitional |
3 |
6 |
Not applicable |
25 |
Gateway 3 applications: new in versus closed applications
| Week commencing |
New in |
Closed applications |
Total cases in progress |
| 6 Apr |
0 |
8 |
132 |
| 13 Apr |
2 |
0 |
129 |
| 20 Apr |
1 |
4 |
124 |
| 27 Apr |
5 |
6 |
121 |
| 4 May |
1 |
2 |
122 |
| 11 May |
5 |
4 |
123 |
| 18 May |
5 |
4 |
122 |
| 25 May |
7 |
1 |
127 |
| 1 Jun |
3 |
1 |
126 |
| 8 Jun |
2 |
0 |
124 |
| 15 Jun |
7 |
0 |
130 |
| 22 Jun |
0 |
0 |
129 |
| Description |
Total |
| Applications in progress |
129 |
| Approvals |
26 |
| Applications received |
38 |
- While no new build projects that have passed through gateway 2 have yet reached gateway 3, a significant number of internal refurbishment projects have already progressed through gateway 2.
- Of the 277 gateway 3 applications received, 221 are category A or B refurbishment projects, with most of the remainder being transitional cases.
- Of the refurbishment cohort, 124 applications have been determined with an approval rate of 86% and a median determination time of 16 weeks.
- The quickest determination time recorded was 8 weeks.
- Gateway 3 remains an important area for BSR, particularly for new build projects. Determination times are expected to reduce as new processes are introduced and additional resource becomes available.