Contracts for Difference (CfD) Allocation Round 7: Sustainable Industry Reward – draft guidance for offshore wind projects

Draft guidance for offshore wind projects on monitoring the implementation of Sustainable Industry Rewards and minimum standards.

Documents

Draft guidance for fixed bottom and floating offshore wind projects on monitoring the implementation of Sustainable Industry Rewards and minimum standards (version 2)

Request an accessible format.
If you use assistive technology (such as a screen reader) and need a version of this document in a more accessible format, please email alt.formats@energysecurity.gov.uk. Please tell us what format you need. It will help us if you say what assistive technology you use.

Details

The CfD Sustainable Industry Reward (SIR) process will be run as a competitive allocation for extra revenue support 6 months before the main CfD auction.

Applicants for all fixed bottom or floating offshore wind generating stations are required to show that their SIR application has met the minimum standards. This guidance sets out how delivery of SIR commitments (including meeting the minimum standards) will be monitored and assessed.

This is a draft document. It’s subject to change and will continue to be revised ahead of the launch of the SIR scheme. New versions will be added to GOV.UK on a rolling basis. Industry will be notified via Renewables UK and Scottish Renewables, and via the CfD stakeholder bulletin.

Published 13 March 2024
Last updated 9 May 2024 + show all updates
  1. Updated the draft guidance for offshore wind projects.

  2. First published.